Installation Guide for FibeAir IP-20F
Page 60 of 63
Ceragon Proprietary and Confidential
9.3
Radio Link Commissioning Procedure
9.3.1
Scope
This section describes the recommended commissioning tests for IP-20 radio link in a
1+0 configuration.
The purpose of the commissioning tests is to verify correct and proper operation of the
product.
9.3.2
Commissioning Test
The following tests should be performed on each installed link.
9.3.2.1
Link Verification
•
Received Signal Level (RSL) is up to +/- 4 dB from the expected (calculated)
level at both ends of the link.
•
Radio Bit Error Rate (BER) is 10E-11 or lower.
•
If working with ATPC, ATPC is operating as expected (RSL = reference level).
9.3.2.2
Ethernet Line Interfaces Test
•
Connect Ethernet Packet Analyzer to the GbE port. Use physical loop at
remote end (or connect second analyzer). Run Packet Loss test for at least one
hour (load rate as per Ceragon's specifications for the chosen MRMC).
•
Connect Ethernet Packet Analyzer to the FE port. Use physical loop at remote
end (or connect second analyzer). Run Packet Loss test for at least one hour
(load rate as per Ceragon's specifications for the chosen MRMC).
Interoperability Verification
•
Connect customer end equipment to the line interfaces, and verify correct
operation.
•
Further interoperability tests should be performed in accordance with the
specific requirements of the connected end equipment.
9.3.2.3
Management Verification
•
Launch the HTTP management and verify that you can manage the link and
that you are able to perform changes to the link configuration (frequency
channel, Tx power, system name, time & date, etc.)
•
Verify that correct parameters are reported when performing the above.
•
Verify that there are no active alarms on the link.
•
If the management station is located at a remote site (Network Operation
Center), verify that the management station can manage the link and receive
traps.