9.
System Commissioning
When the system has been installed, the functionality should be tested thoroughly as follows:
1.
Charge the PSDs.
2.
Verify that the MSD is in a protective secondary enclosure suitably rated for the environment.
3.
Inspect all wiring to ensure it is correct, secure, and neatly restrained according to good engineering
practice and compliant with all local and national rules.
4.
Any metallic conduit that was used should be suitably cross bonded when connecting to a
non-metallic enclosure.
5.
Verify that appropriate supply protection has been installed to the MSD.
6.
Verify that the correct operating voltage is being applied, 24Vdc to the MSD, and that the polarity is
correct; higher voltages require the optional power supply.
7.
Verify that the MSD reset switch has been installed and is accessible to the operators.
8.
Verify that the antenna is mounted correctly and in such a way that it has good line of sight to the
operating area and that the cables are secure.
9.
Apply power and observe that the MSD powers up correctly and the LCD is displaying
‘LINKED
PSD NONE.’
10.
Verify that the machine can be started as normal.
11.
Verify that each of the existing fixed E-Stop switches still operate correctly.
12.
Link each of the PSDs in turn. Verify that each links correctly and operates the E-Stop correctly.
13.
Ensure operators are trained in the use and features of the system, particularly in the use of the battery
charger, logging on and logging off requirements, activation and release of the E-Stop switch, use of the
belt clip, and understanding the operating range and consequences of exceeding the operating range,
use of the MSD reset switch in the event of a prolonged communication loss, and expectations to
maintain the equipment in good operating order.