Internal Wiring
Check all electrical connections in unit control boxes. Tighten
as required.
Refrigerant Service Ports
Each unit system has two
1
/
4
-in. SAE flare (with check valves)
service ports: one on the suction line, and one on the compres-
sor discharge line. Be sure that caps on the ports are tight.
Compressor Rotation
On 3-phase units with scroll compressors, it is important to be cer-
tain compressor is rotating in the proper direction. To determine
whether or not compressor is rotating in the proper direction:
1. Connect service gages to suction and discharge pressure
fittings.
2. Energize the compressor.
3. The suction pressure should drop and the discharge pres-
sure should rise, as is normal on any start-up.
If the suction pressure does not drop and the discharge pressure
does not rise to normal levels:
4. Note that the evaporator fan is probably also rotating in
the wrong direction.
5. Turn off power to the unit and install lockout tag.
6. Reverse any two of the unit power leads.
7. Re-energize to the compressor. Check pressures.
The suction and discharge pressure levels should now move to
their normal start-up levels.
NOTE: When the compressor is rotating in the wrong direction,
the unit will make an elevated level of noise and will not provide
cooling.
Cooling
Set space thermostat to OFF position. To start unit, turn on
main power supply. Set system selector switch at COOL posi-
tion and fan switch at AUTO. position. Adjust thermostat to a
setting below room temperature. Compressor starts on closure
of contactor.
Check unit charge. Refer to Refrigerant Charge section on
page 15.
Reset thermostat at a position above room temperature. Com-
pressor will shut off. Evaporator fan will shut off after a
30 second delay.
To shut off unit, set system selector switch at OFF position.
Resetting thermostat at a position above room temperature
shuts unit off temporarily until space temperature exceeds ther-
mostat setting.
Heating
To start unit, turn on main power supply. Set system selector
switch to the HEAT position and set thermostat at a setting
above room temperature. Set fan to AUTO position.
First stage of thermostat energizes the first stage of the electric
heaters. Second stage of thermostat energizes the second stage
of electric heaters (if installed). Check heating effects at air
supply grille(s).
If electric heaters do not energize, reset limit switch (located on
supply-fan scroll) by pressing button located between termi-
nals on the switch.
To shut unit off, set system selector switch to the OFF position.
Resetting thermostat at a position below room temperature
temporarily shuts unit off until space temperature falls below
thermostat setting.
Ventilation (Continuous Fan)
Set fan and system selector switches at ON and OFF positions,
respectively. Evaporator fan operates continuously to provide
constant air circulation. When the evaporator-fan selector
switch is turned to the OFF position, there is a 30 second delay
before the fan turns off.
START-UP, PREMIERLINK CONTROLS
Use the Carrier network communication software to start up
and configure the PremierLink controller.
Changes can be made using the ComfortWORKS
®
software,
ComfortVIEW™ software, Network Service Tool, System Pi-
lot™ device, or Touch Pilot™ device. The System Pilot and
Touch Pilot are portable interface devices that allow the user to
change system set-up and set points from a zone sensor or termi-
nal control module. During start-up, the Carrier software can also
be used to verify communication with PremierLink controller.
NOTE: All set-up and set point configurations are factory set and
field adjustable.
For specific operating instructions, refer to the literature pro-
vided with user interface software.
Perform System Check-Out
1. Check correctness and tightness of all power and commu-
nication connections.
2. At the unit, check fan and system controls for proper
operation.
3. At the unit, check electrical system and connections of any
optional electric reheat coil.
4. Check to be sure the area around the unit is clear of con-
struction dirt and debris.
5. Check that final filters are installed in the unit. Dust and
debris can adversely affect system operation.
6. Verify that the PremierLink controls are properly con-
nected to the CCN bus.
CAUTION
EQUIPMENT DAMAGE HAZARD
Failure to follow this caution can result in premature wear
and damage to equipment.
Scroll compressors can only compress refrigerant if rotat-
ing in the right direction. Reverse rotation for extended
times can result in internal damage to the compressor.
Scroll compressors are sealed units and cannot be repaired
on site location.
WARNING
ELECTRICAL OPERATION HAZARD
Failure to follow this warning could result in personal inju-
ry or death.
The unit must be electrically grounded in accordance with
local codes and NEC ANSI/NFPA 70 (American National
Standards Institute/National Fire Protection Association).
IMPORTANT: SET-UP INSTRUCTIONS
All set-up and set point configurations are factory set and
field-adjustable.
Refer to
PremierLink™ Installation, Start-Up and Con-
figuration Instructions
for specific operating instructions
for the controller. Have a copy of this manual available at
unit start-up.
Содержание WeatherMaster 50HC04
Страница 32: ...32 Fig 63 RTU Open Overlay for Economizer Wiring ...
Страница 33: ...33 Fig 64 VFD Overlay for W2770 Controller Wiring ...
Страница 85: ...85 Fig B 50HC A04 A06 PAC Control Diagram 208 1 60 208 230 3 60 460 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 86: ...86 Fig C 50HC A07 PAC Control Diagram 208 230 3 60 460 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 89: ...89 Fig F 50HC D08 D09 PAC Control Diagram 208 230 3 60 460 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 90: ...90 Fig G 50HC D11 PAC Control Diagram 208 230 3 60 460 3 60 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 91: ...91 Fig H 50HC D12 PAC Control Diagram 208 230 3 60 460 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 92: ...92 Fig I 50HC D14 PAC Control Diagram 208 230 3 60 460 3 60 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 93: ...93 Fig J 50HC A04 A06 PAC Power Diagram 208 230 1 60 APPENDIX D WIRING DIAGRAMS ...
Страница 94: ...94 Fig K 50HC A04 A06 PAC Power Diagram 208 230 3 60 460 3 60 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 95: ...95 Fig L 50HC A07 PAC Power Diagram 208 230 3 60 460 3 60 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 98: ...98 Fig O 50HC D07 PAC Power Diagram 575 3 60 6 Ton 2 Stage with Dehumidification APPENDIX D WIRING DIAGRAMS ...
Страница 99: ...99 Fig P 50HC D08 D09 PAC Power Diagram 208 230 3 60 460 3 60 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 100: ...100 Fig Q 50HC D11 PAC Power Diagram 208 230 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 101: ...101 Fig R 50HC D11 PAC Power Diagram 460 3 60 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 102: ...102 Fig S 50HC D12 PAC Power Diagram 208 230 3 60 460 3 60 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 103: ...103 Fig T 50HC D14 PAC Power Diagram 208 230 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 104: ...104 Fig U 50HC D14 PAC Power Diagram 460 3 60 575 3 60 APPENDIX D WIRING DIAGRAMS ...
Страница 109: ...109 Fig Z 50HC D12 PAC Control Diagram 230 460 575 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 110: ...110 Fig AA 50HC D14 PAC Control Diagram 230 460 575 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 111: ...111 Fig AB 50HC A04 A06 PAC Power Diagram 208 230 1 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 112: ...112 Fig AC 50HC A04 A06 PAC Power Diagram 208 230 460 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 113: ...113 Fig AD 50HC A04 A06 PAC Power Diagram 575 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 114: ...114 Fig AE 50HC A07 PAC Power Diagram 208 230 460 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 115: ...115 Fig AF 50HC A07 PAC Power Diagram 575 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 116: ...116 Fig AG 50HC D08 D09 PAC Power Diagram 208 230 460 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 117: ...117 Fig AH 50HC D08 D09 PAC Power Diagram 575 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 118: ...118 Fig AI 50HC D11 PAC Power Diagram 208 230 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 119: ...119 Fig AJ 50HC D11 PAC Power Diagram 460 3 60 575 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 121: ...121 Fig AL 50HC D14 PAC Power Diagram 208 230 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 122: ...122 Fig AM 50HC D14 PAC Power Diagram 460 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 123: ...123 Fig AN 50HC D14 PAC Power Diagram 575 3 60 with Humidi MiZer System APPENDIX D WIRING DIAGRAMS ...
Страница 124: ...124 Fig AO PremierLink System A04 A06 Wiring Diagram APPENDIX D WIRING DIAGRAMS ...
Страница 125: ...125 Fig AP RTU Open System Control A04 A06 Wiring Diagram APPENDIX D WIRING DIAGRAMS ...
Страница 126: ...126 Fig AQ PremierLink System A07 D14 Wiring Diagram APPENDIX D WIRING DIAGRAMS ...
Страница 127: ...127 Fig AR RTU Open A07 D14 Wiring Diagram APPENDIX D WIRING DIAGRAMS ...