INSTALL SPRING ISOLATION
Spring isolation may be purchased as an accessory from
Carrier for field installation. It may also be field supplied and
installed. Spring isolators may be placed directly under
machine support plates or located under machine soleplates.
See Fig. 49. Consult job data for specific arrangement. Low
profile spring isolation assemblies can be field supplied to keep
the machine at a convenient working height.
Obtain specific details on spring mounting and machine
weight distribution from job data. Also, check job data for
methods to support and isolate pipes that are attached to spring
isolated machines.
NOTE: These isolators are not intended for seismic duty, but
are intended to reduce the vibration and noise levels transmit-
ted from the chiller to the surrounding environment. For instal-
lations adjacent to areas that are sensitive to noise and/or
vibration, use the services of a qualified consulting engineer or
acoustics expert to determine whether these springs will pro-
vide adequate noise/vibration suppression.
Step 6 — Connect Piping
INSTALL WATER PIPING TO HEAT EXCHANGERS —
Refer to Table 7 for nozzle sizes. Install piping using job data,
piping drawings, and procedures outlined below. A typical pip-
ing installation is shown in Fig. 50.
1. Offset pipe flanges to permit removal of waterbox cover
for maintenance and to provide clearance for pipe clean-
ing. No flanges are necessary with marine waterbox
option; however, water piping should not cross in front of
the waterbox cover or access will be blocked.
2. Provide openings in water piping for required pressure
gages and thermometers. For thorough mixing and
temperature stabilization, wells in the leaving water pipe
should extend inside pipe at least 2 in. (51 mm).
3. Install air vents at all high points in piping to remove air
and prevent water hammer.
4. Install pipe hangers where needed. Make sure no weight
or stress is placed on waterbox nozzles or flanges.
5. Water flow direction must be as specified in Fig. 51-53.
NOTE: Entering water is always the lower of the 2 noz-
zles. Leaving water is always the upper nozzle for cooler
or condenser.
6. Install waterbox vent and drain piping in accordance with
individual job data. All connections are
3
/
4
-in. FPT.
7. Install waterbox drain plugs in the unused waterbox
drains and vent openings.
8. Install optional pumpout system or pumpout system and
storage tank as shown in Fig. 54-58.
IMPORTANT: Accessory spring isolation packages are
intended solely for non-seismic applications. Seismic
applications must be designed by a registered professional
in accordance with all applicable national and local codes.
IMPORTANT: Chiller water nozzle connections to be
designed by others in accordance with all applicable
national and local codes.
CAUTION
Remove cooler and condenser liquid temperature and
optional pressure sensors before welding connecting piping
to water nozzles. Refer to Fig. 6-8. Replace sensors after
welding is complete.
Fig. 49 — 23XRV Accessory Spring Isolation
(Shown with Accessory Soleplates)
NOTE: The accessory spring isolators are supplied by Carrier for
installation in the field.
a23-1537
CAUTION
Factory-supplied insulation is not flammable but can be
damaged by welding sparks and open flame. Protect insu-
lation with a wet canvas cover.
CAUTION
Never charge liquid R-134a refrigerant into the chiller if
the pressure is less than 35 psig (241 kPa). Charge as a gas
only, with the cooler and condenser pumps running, until
35 psig (241 kPa) is reached using the pumpdown mode on
the ICVC. Terminate the pumpdown mode using the
ICVC. Flashing of liquid refrigerant at low pressures can
cause tube freeze-up and considerable damage.
AIR VENT
ENTERING
CHILLED
WATER
LEAVING
CHILLED
WATER
LEAVING
CONDEN
S
ER
WATER
ENTERING
CONDEN
S
ER
WATER
PRE
SS
URE
GAGE
S
I
S
OLATION VALVE
S
I
S
OLATION VALVE
S
Fig. 50 — Typical Nozzle Piping
1016
Содержание EVERGREEN 23XRV
Страница 53: ...53 Fig 60 Typical Field Wiring Schematic LF 2 VFD Shown NOTE See Notes for Fig 60 on page 56 ...
Страница 54: ...54 Fig 60 Typical Field Wiring Schematic LF 2 VFD Shown cont a23 1585 ...
Страница 55: ...55 Fig 60 Typical Field Wiring Schematic LF 2 VFD Shown cont a23 1586 ...
Страница 60: ...60 Fig 63 23XRV Controls Schematic LF 2 ...
Страница 63: ...63 SEE NEXT PAGE SEE NEXT PAGE SEE NEXT PAGE Fig 67 23XRV Controls Schematic Rockwell Standard Tier VFD Shown ...
Страница 64: ...64 FROM PREVIOUS PAGE Fig 67 23XRV Controls Schematic Rockwell Standard Tier VFD Shown cont ...
Страница 73: ...73 Fig 78 Lead Lag Control Wiring Parallel Flow Application Unit with R Compressor Shown a23 1597 ...
Страница 74: ...74 Fig 79 Lead Lag Control Wiring Series Flow Application Unit with R Compressor Shown a23 1598 ...