Points to note at installation
Take note of the following points when installing the host machine.
1) Moving the host machine from a low-temperature place to a warm plate can generate
condensation, resulting in sweat on metal surface.
Image fault can occur if using the host machine while condensation built up.
When moving the host machine from a low-temperature place to a warm place for
installation, be sure to unpack the host machine and leave it for 2 hours or more so that the
host machine becomes comfortable with the room temperature.
2) Checking installation site
Since this machine weighs approx. 500 kg, be sure to check that the floor at the installation
site is durable enough.
3) Be sure to get 2 people or more to install the host machine.
4) Sequence to turn ON the power when the pickup/delivery options are connected.
Be sure to follow the correct order to turn ON the power, otherwise the host machine fails
to recognize the options, resulting in an error.
< Correct order to turn ON the power >
1. Pickup/delivery options
2. Host machine
NOTE:
There is no specified order to turn ON the power among options.
< Correct order to turn OFF the power >
1. Host machine
2. Pickup/delivery options
CAUTION :
Points to note when turning OFF the main power switch
When turning off the main power, make sure to go through the following procedure to
protect the hard disk of this product.
1. Press the power switch on the control panel for 3 sec or more.
2. Work on the touch panel by following the instructions on the shutdown sequence
screen.
3. A message is shown telling “Executing shutdown”.
Once a message, which tells that the power of the option devices can be turned off,
is shown on the control panel of the host machine, turn OFF the power switch of the
pickup/delivery options.
NOTE:
• The machine performs cooling-down inside the machine while shutdown is in progress.
(To avoid possible trouble such as light image density due to toner deterioration/
coagulation and image fault)
• The shutdown process can take up to 60 minutes.
(The main power switch of the host machine is automatically turned OFF once the
shutdown process is complete)
• There is no function to forcibly turn OFF the main power while shutdown process is in
progress.
Turning OFF the main power at normal servicing:
When turning OFF the main power switch at normal servicing (at installation, periodical
maintenance, etc), wait for the following screen to be appeared after the start of
shutdown process, and then manually turn OFF the main power switch.
F-9-12
CAUTION :
• Turning OFF the main power switch manually while shutdown process in progress
may cause trouble to the hard disk of this product.
• In case that the main power is manually turned OFF frequently for a day, keep the
fixing feed unit pulled out when turning OFF the power so that theaforementioned
image trouble can be avoided.
• When turning ON the main power switch again, be sure to turn it ON after the main
power lump on the control panel goes OFF. Note that during the main power lump
comes ON, the power status of this equipment is ON.
4. The main power switch automatically goes OFF when the shutdown process is
complete.
Содержание imagePRESS 1110
Страница 242: ...3 3 Periodical Service Periodical Service Periodical service item ...
Страница 655: ...5 5 Adjustment Adjustment Overview When replacing parts Major adjustment ...
Страница 733: ...7 7 Error Code Error Code Overview Location Code Pickup Position Code Pickup size Error Code Jam Code Alarm Code ...
Страница 944: ...8 8 Service Mode Service Mode Overview COPIER FEEDER SORTER BOARD Situation Mode ...
Страница 1555: ... Service Tools General Circuit Diagram General Timing Chart Operator Maintenance Appendix ...