Chapter 8: Acceptance & Commissioning Procedures
PTP 820 Commissioning Log
phn-3962 004v000
Page 8-11
PTP 820 Commissioning Log
The Commissioning Log is an integral part of the commissioning procedure and should be filled in
for each installed link.
The Commissioning Log gathers all relevant information regarding the installed link and contains a
checklist of all recommended commissioning tests.
Maintaining the Commissioning Log is important for tracking your installations, and to provide
essential data for Cambium Networks.
Upon completing the Commissioning Log, send the log to Cambium
Networks’
support center at
https://support.cambiumnetworks.com
PTP 820 LINK COMMISSIONING LOG
1. GENERAL INFORMATION
Customer:
Radio model:
Configuration:
Radio link code:
Site 1 name & add:
Site 2 name & add:
2. ODU/RFU
Site 1
Site 2
ODU model:
ODU p/n:
ODU s/n:
ODU SW:
Tx frequency (MHz):
Rx frequency (MHz):
Link ID:
Tx power (dBm):
ATPC on/off:
ATPC ref level:
ODU Polarization:
3. ANTENNA AND ODU
MOUNT
Site 1
Site 2
Antenna vendor and model:
Antenna size:
Mounting type:
Содержание PTP 820C
Страница 1: ...INSTALLATION GUIDE PTP 820C and PTP 820C Assured System Release 10 0 ...
Страница 8: ...Contents phn 3962 004v000 Page vi Scope 8 9 Commissioning Test 8 9 PTP 820 Commissioning Log 8 11 ...
Страница 29: ...Chapter 2 Product Hardware Description MultiCore Mediation Devices MCMD phn 3962 004v000 Page 2 5 Figure 5 OMT ...
Страница 31: ...Chapter 2 Product Hardware Description PoE Injector phn 3962 004v000 Page 2 7 Figure 7 PoE Injector Ports ...
Страница 33: ...Chapter 2 Product Hardware Description System Components phn 3962 004v000 Page 2 9 ...
Страница 193: ...Chapter 6 Installation Procedures per Configuration Type AFR 1 0 Hub Site phn 3962 004v000 Page 6 92 ...