ANNEX 3 WEEKLY PREVENTIVE MAINTENANCE SCHEDULE
All important parts of the unit must be maintained as per the preventive
maintenance schedule to honor the warranty and to avoid possible defects.
Adequate maintenance will extend the life of the coffee machine and deliver a
consistent high quality beverage.
A
n
n
ex
3
WEEKLY MAINTENANCE
Verify the filter paper level.
Sanitize the brew chamber with a hot water cycle.
Sanitize the soluble mixing bowl with a hot water cycle.
Capture data from the software.
Verify the overflow cup.
Verify the overflow drip tray.
PREVENTIVE MAINTENANCE SCHEDULE AT DIFFERENT CYCLES
5,000 cycles
Clean the brew group with a commercial urn cleaner.
10,000 cycles
Check & replace the outlet valves.
Check & replace the water filter.
25,000 cycles
Replace the brew group via Cafection’s Brew Group Exchange Program.
Replace the whipping motor(s).
50,000 cycles
Delime the water tank & outlet valves.
100,000 cycles
Replace the grinder burrs.
Replace the water tank float, the heater switch & the water level switch.
PERFORMED BY THE
SER