Installing assembled frames
The assembled frames can now be positioned back in to the excavated areas. Using the existing string line, ensure the L
supports side of the pool are perfectly aligned, if not, make the necessary adjustments. Care must be taken to ensure the
measure between the centers. It is advisable to hold the posts into position using steel pegs. Frames installed in such a way
that no horizontal part of the L support is situated higher that the surrounding ground level.
The levelling of the assembled frame is an important exercise that must be done precisely and repeatedly until correct.
When all the assembled frames have been positioned and levelled you need to recheck and ensure that the back of the L supports
are all in line and the diagonal measurements of the assembled frames are all correct and equal.
Before proceeding check the measurements for the width of the pool between the inside of the assembled frames should be as per
table below. The width measurements A can have a variance of + or
–
5mm.
If all of the measurements and levels are correct you can now proceed with the backfill of the channels across the pool and cement
mix at the end of the channels.
When positioning the L Supports for your pool, it is important that the supports are supported and retained in a perpendicular
position while the excavation is being packed.
A simple and effective way to achieve this is to drive a star picket into the ground at the rear of the L support, then temporarily
attach the L support to the star picket with some duct tape. This will hold the post vertical while the cement and backfill is put into
place.
Note:
top of the horizontal L supports and ground should be level.
Model Size
White pool 490
8011015
White pool 610
8011012
White pool 730
8011013
White pool 910
8011014
Distance A
3440mm
3440mm
3440mm
4390mm
21
22
150mm
ground line