Placing the heating system in operation
Logano G234X – 6 720 811 233 (2017/02)
22
Checking the AquaSmart
TM
30. Check operation of the maximum AquaSmart
TM
setting to make sure
that it switches the boiler off as soon as the boiler temperature set
on the AquaSmart
TM
is reached. Record the result in the
commissioning report (
– Set the AquaSmart
TM
to the desired setting.
– Replace the front wall of the boiler (
Fig. 28 Checking temperature control
[1]
Adjustment keypad
6.6
Shutting off gas supply to boiler
▶ Set the room thermostats to the lowest setting.
▶ Disconnect the heating system from the power supply before
carrying out maintenance work.
▶ Turn the gas valve ON/OFF knob (
OFF
position. Do not use excessive force.
6.7
Inform owner/operator, hand over technical
documentation
▶ Familiarize the owner/operator with the entire heating system and
the operating instructions for the boiler.
▶ Hand over the technical documentation to the owner/operator.
▶ Jointly sign the commissioning report.
6 720
8
04 440-2
8
.1T
1
Содержание G234X/38
Страница 34: ...10 Logano G234X 6 720 811 233 2017 02 34 Notes...
Страница 35: ...10 Logano G234X 6 720 811 233 2017 02 35 Notes...
Страница 36: ......