BÜCHI Labortechnik AG
Installation | 5
Operation Manual Rotavapor® R-300
23/116
5
Installation
5.1
Installation site
The installation site must meet the following requirements:
NOTICE
Risk of property damage due to overheating
u
Do not run any cables under the heating bath.
Firm and level surface
Space requirements: at least 620 mm x 510 mm (W x D)
Clear access to mains switch and power supply cable.
(Note: it must be possible to switch off the equipment involved in the distillation
process and disconnect the electrical connections at any time.)
If distilling under vacuum, there must be fume extraction apparatus available.
Wherever possible, the Rotavapor® R-300 should be set up inside a fume hood. If
that is not possible for reasons of space, it can also be set up outside if the safety
guard (optional accessory) is fitted and the residual vapors are fed into the fume
hood.
5.2
Securing against earthquakes
The Rotavapor R-300 has an earthquake fixing to protect the device against falling.
1
Fig. 6: Earthquake fixing
1
Lashing eye
u
Lie the Rotavapor R-300 on its back.
u
Fix the lashing eye (1) to the base of the R-300 from underneath using a screw.
There is a threaded hole provided for the purpose.
u
Tie the lashing eye to a fixed point using strong cord or a wire.