69
Technical data
and start-up
EVB1-350/400-40-HP
9.2
Building HV Supply
The building of the HV wiring must be carried out in accordance with the following instructions. Here it is important
that no strands are damaged and that none stick out at the sides on the assembled cable. So check that the screw
connections are correct for each completed cable and that the cable lug is fixed properly (pull test).
For the HV connections we recommend:
A shielded, insulated automotive cable (e.g. Huber & Suhner).
Cable lug, for the type see chapter
To assemble the cable lugs, using the appropriate crimping tool is absolutely necessary!
PROCEDURE STEP
ILLUSTRATION / OTHER INFORMATION
1.
Insulate 35 mm of the HV cable (1).
Ensure that you do not damage the shielding
braid underneath it!
2.
Shorten the shielding braid (1) by 20 mm.
The cable-side shielding braid (2) must be a
length of around 15 mm.
Содержание EVB1-350-40-HP
Страница 33: ...33 Technical data and start up EVB1 350 400 40 HP 6 6 1 EVB1 400 350 40 HP Block Circuit Diagram...
Страница 42: ...Technical data and start up EVB1 350 400 40 HP 42 6 9 2 Control via Terminal 15 with Driving via CAN...
Страница 98: ...Technical data and start up EVB1 350 400 40 HP 98 V Validity of the Manual 3...