REFRESH
INSTALLATION, OPERATION AND MAINTENANCE MANUAL
Assembly, Installation and Commissioning
2.3.3
Refresh Ultima Installation Procedures
2.3.3.1 Installing the Canopy
Please note the following step guidelines must be taken into consideration during the installation of
BKV products.
WARNING:
COMPETENT PERSONNEL FAMILIAR WITH THE ASSESSMENT OF HAZARDS AND RISKS
ASSOCIATED WITH INDUSTRIAL ELECTRICAL AND VENTILATION EQUIPMENT SUCH AS
FANS AND AIR HANDLING UNITS SHOULD INSTALL THIS EQUIPMENT.
WARNING:
ENSURE STEPS, PODIUM STEPS, SCISSOR LIFT OR MOBILE SCAFFOLD TOWER ARE
SECURE AND STABLE BEFORE USE.
Step 1:
Check the Services Tower and the canopy are correctly assembled. Refer to
2.2.4 Refresh Mini, Midi & Maxi Assembly Procedures
Step 2:
Position the steps, podium steps, scissor lift or mobile scaffold tower as necessary to
aid installation.
Step 3:
Safely secure the canopy to the lifting equipment.
WARNING:
USE LIFTING EQUIPMENT WHICH HAS A SUITABLE SAFE WORKING LOAD FOR
THE EQUIPMENT BEING LIFTED.
Step 4:
Using the lifting equipment, raise the canopy to the correct height then using the
adjustable support stands safely support the canopy.
Step 5:
Using the location holes on the Services Tower and the canopy, locate the two items
together and then use the M6 fixings to secure. Using the spanner tighten the M6
fixings until fully secure.
Step 6:
Using the holes in the canopy and the double-skinned support leg, locate the two items
together and then use the M6 fixings to secure. Using the spanner tighten the M6
fixings until fully secure.
Step 7:
Using a spirit level, check the lateral position of unit.
Step 8:
Where applicable, using the battery powered equipment, Unistrut and fixings from the
fixings box, mount the canopy to the wall.
Step 9:
Using screws, plugs or anchors, fix the canopy to the wall. Using a suitable tool, tighten
until the canopy is fully secure.
WARNING:
MAKE SURE THE CANOPY IS FULLY SECURED BEFORE REMOVING THE
SUPPORT STANDS.
Step 10:
Slowly
lower down the support stands approximately 50mm and make sure the canopy
is fully secured to the Services Tower and double-skinned support leg and also to the
wall (as necessary). Further tighten the all fixings as necessary.
Step 11:
Connect the main power lead to the incoming power supply.
Step 12:
Peel back the poly coat to expose canopy joints. Do not remove protective film from the
canopy. This will be done by others.
Step 13:
Using the silicone sealant, seal:
Step a)
Joins in the unit
Step b)
Joints between walls and ceilings (where necessary).
Step 14:
Install the required filters, blanks and panels into correct openings and positions.
Step 15:
Complete the “On site final inspection” checklist.
Issue: Final
Page 23 of 70
Содержание Refresh Maxi
Страница 71: ......