3 Commissioning
Page
20
of
28
Original installation instructions Hyperion Lithium Ion Energy Storage
Chapter 6.5: Connecting battery communication cable:
▪
yellow:
CAN H
(E)
▪
white:
CAN L
(D)
▪
red:
Enable
(B)
▪
black:
GND
(C)
Chapter 6.1.2: Interior View
▪
Yellow-green grounding point for grounding the battery (L)
Chap. 6.8 DC connection
▪
Red
(+)
(A+)
▪
Black
(-)
(A-)
It is recommended to use all bridges (30 A)
3.
Check all electrical connections
4.
Close the housing of the inverter.
3.4.2
Kostal PLENTICORE plus
1.
In order to operate the Hyperion storage system communicatively with
the Kostal PLENTICORE plus, the communication must be switched to
RS485.
Disconnect the X2 plug from the
BMS master (green plug at top left).
Pin the yellow wire from PIN1 to
PIN3 (RS485+).
Pin the white wire from PIN2 to
PIN4 (RS485-).
Bridge PIN7 and PIN8 to activate
the RS485 communication.
Plug X2 back into BMS master.
2.
Preparation: Ground the Hyperion housing:
PE
▪
Yellow-green
Connect to grounding rail
Figure 8:
Connecting the
PLENTICORE plus to the
BMZ Hyperion