Installation, assembly and commissioning
for the first time
Version 1.1
Page 91 of 113
4.18
Recommended parameters of the SMA Sunny Island inverter at the time
of installation:
In order to ensure the optimum working range of the battery and to optimise the quantity of storable
energy, the battery manufacturer has given the following recommendations for the parameters of the
inverter:
A detailed description of parameters is given in the operating manual of your SMA Sunny Island
inverter.
Amongst the recommended parameters, we differentiate between “On-grid” and “Off-grid”
applications.
4.18.1
On-grid application
1.
Enter the following values in the quick configuration guide during the basic configuration of the
Sunny
Island inverter (see the documentation of the system):
Battery type
BatTyp
: LiIon_Ext-BMS
Battery capacity
BatCpyNom
: 105 Ah (C10)
2.
After the basic configuration of the
Sunny remote control, turn the knob and select the
input page
password (1/1)
.
3.
Press the knob. This will take you to the input page.
4.
Calculate the checksum of the
Runtime
operating hours. Determine the installer password.
Example: The
Runtime
operating hours are
1234 h
. The checksum is the sum of all digits:
1 + 2 + 3 + 4 =
10
5.
Select
Set
on the Sunny remote control and press the knob.
6.
Set the determined installer password and press the knob.
The Sunny remote control is in the installer mode.
7.
Select the
700# Operator Level
menu and press the
knob.
8.
Select the
700.01 ActLev
parameter, press the knob
and set to
Expert
.
9.
Confirm the
<accept Y/N>
query with
Y
.
10.
Set the following parameters to the specified values only if the Sunny
Island units are used in systems for
own consumption optimisation
:
Содержание ESS 7.0
Страница 1: ...OPERATING MANUAL ESS 7 0 ...
Страница 2: ...Version 1 1 Original operating manual ...
Страница 110: ...Annexe Version 1 1 Page 110 of 113 10 1Declaration of conformity Figure 10 1 EC Declaration of Conformity ...
Страница 111: ...Annexe Version 1 1 Page 111 of 113 10 2Warranty card Figure 10 2 warranty card ...
Страница 112: ...Annexe Version 1 1 Page 112 of 113 10 3Installation check list Figure 10 3 installation check list ...
Страница 113: ...Annexe Version 1 1 Page 113 of 113 Figure 10 4 installation check list part 2 ...