INSTALLATION AND MAINTENANCE
INSTALLATION PLACE REQUIREMENT
Equipment should be installed indoors, with clean, adequate light and a good air circulation environment. It is
prohibited to be installed in the environment of exposure to sunlight, rain, water vapour, moisture, corrosive
gas, explosive gas and dust.
Environment temperature should be lower than 40
℃,
humidity lower than 70
℃
(preferably, install air
conditioner for cooling and drying). Environment temperature too high may lead to equipment cease and
lower ozone generator production. High humidity may lead to controlling circuit malfunction or damage.
The distance between equipment and wall, ceiling should be more than 600mm, which is convenient for
future maintenance.
Equipment should be installed on solid, horizontal ground. Installing on uneven ground may lead to a high
level of equipment noise and vibration.
PIPING INSTALLATION
●
Gas input pipe
○
DN20 PVC or 12*8 PU pipe is suggested. The inner diameter needs to be over 15mm if the
gas source is air and over 8mm if it is oxygen.
●
Cooling water pipe
○
DN20 PVC is suggested. The inner diameter needs to be over 10mm.
●
Ozone output pipe
○
304/316 stainless steel pipe or PTFE pipe is suggested. The inner diameter needs to be
over 15mm if the gas source is air and over 8mm if the gas source is oxygen. Otherwise, the
inner pressure is too high which will lead to arcing, and main circuit board damage.
ELECTRICAL CONNECTION
●
The connection cable size should not be less than specified in the specification, and when cable
length is more than 10 meters, a bigger size should be used.
●
The power source should meet the voltage and frequency requirement.
●
The voltage fluctuation cannot be too high, and it should be within the range of -10%~+10% of the
nominal voltage. It cannot be used if voltage is out of range, otherwise it will cause equipment
damage, and voltage stabiliser or regulator should be used to meet the voltage range.
●
Voltage unbalance of the three phases cannot be too high, and should be within 5%. Stabiliser
should be used if there is high fluctuation.
ON / OFF PROCEDURE
●
Check before operation: check whether equipment input piping, cooling water piping, ozone output
piping are in good connection, whether power sources meet the equipment voltage requirement.
11
Содержание AQUAZONE 200G
Страница 8: ...7...
Страница 10: ...200G 400G AND 600G INTERFACE TWO SETS MODULAR DESIGN 9...
Страница 11: ...4 20MA ANALOG SIGNAL RECEIVING PORT 10...
Страница 17: ...CONTACT US 16...