![BIO RAD S3e Скачать руководство пользователя страница 12](http://html1.mh-extra.com/html/bio-rad/s3e/s3e_user-manual_2753179012.webp)
12
Initial Set Up: Quality Control
(≈ 10 minutes)
In case you are not the first user of the current day, please confirm with the previous
user whether a low-pressure cleaning final set up has been performed. If so, skip both
start-up and quality control procedures. NEVERTHELESS, DO NOT FORGET TO CHECK THE
FLUIDICS. IF NEEDED, PERFORM THE “HOT SWAP” PROCEDURE
1.
Vortex a bottle of ProLine Calibration Beads and place 8-10 drops into a 5 ml
sorter tube. Do not dilute these particles.
2.
Place the tube with beads into the sample input station and move the loading
stage into the run position
3.
Click in the
Run QC
button in the
Setup and Maintenance
tab
4.
Choose the correct bead lot in the
Bead Lot
dropdown list of the
Quality Control
Process
dialog and then click in the
checkmark
button to begin the
Quality Control
procedure