Preparation of installation
The final installation requires the presence of a BEUMER supervisor for super-
vising the installation and aligning the machine. On site, the supervisor will de-
cide on the way and sequence of installation. The installation sequence depends
on the space available on site and the state of the civil engineering work. There-
fore, the following installation description can only serve as an aid and not as an
obligatory instruction.
It is advisable to have the installation carried out by BEUMER personnel.
We do not assume any liability for damage caused by improper work!
Foundation
The place of installation must be appropriate for the static and dynamic loads
and must be free from vibrations. During project planning, sufficient space
around the machine must be ensured in order to facilitate installation and main-
tenance work.
The positions of the supporting points should be measured and recorded before
installation. This way, the material for backing can be assigned to the respective
supports.
The necessary dimensions are indicated in the installation drawing included in
the annex to these operating instructions.
Tools
The following tools are required for installing the machine:
• Ring spanner (size 8 - 55)
• Open-end spanner (size 8 - 55)
• Torque
wrench
• Welding
machine
• Cutting
torch
• Right-angle
grinder
• Drilling machine, percussion drill
• Measuring instruments: Water level, plummet, measuring tape
• Lifting equipment: crane, fork-lift truck, mechanical winch (5 t), ropes, chains,
fastening devices
Further special tools are not required for installation.