DESCRIPTION

 

Model 450 -60 Reservoir Valve is an automatic control 
valve designed to fill reservoir or tanks and to shut off 
when the water reaches a pre-determined level.

 

The valve opening will modulate, adjusting the fill rate to 
a discharge flow while maintaining a constant upper 
level in the reservoir.

 

An upper control chamber, operating on a two way 
control principle, has varying pressure produced by pilot 
modulation and opens in conjunction with an upstream 
restriction needle valve.

 

If the water rises to a pre-determined level, float action 
will tend to close the pilot valve, and the main valve 
modulates to close

 

 

INSTALLATION

 

1. Allow enough room around the valve assembly for making 
adjustments and for future maintenance / disassembly work.

 

2. Thoroughly flush the pipeline to remove dirt, scale, and 
debris. Failure to perform this operation may render the valve 
inoperable.

 

3. It is recommended that an isolation valve be installed 
upstream of the Bermad control valve to allow for future 
maintenance operations.

 

4. Install the valve in the pipeline with the valve flow arrow on 
the body casting in the proper direction. Use the lifting eye 
provided on the main valve cover for raising and lowering the 
valve. Install the valve horizontally with the cover up for best 
performance.

 

5. After installation carefully inspect /correct any damaged 
accessories, piping, tubing, or fittings

.

 

6. Install the 2 way float pilot valve #22 inside the water tank 
connecting it to the wall 30 cm. above the desire upper water 
level.

 

7. Connect the horizontal port of the float to cock valve #2 
on the valve, using 1/2” pipe. 

 

 

ON LINE STATIC TEST PROCEDURES 

OPEN VALVE: STATIC TEST 

1. Close cock valve #1 and #2 to isolate the pilot control 
system. This prevents dirt exposure in the control loop.

 

2. Remove plug from the cover of the valve.

 

Caution:

 This will allow the valve to fully open. Make sure 

that this condition does not cause system damage! 
3. Check for leaks at the flange connection fittings etc.

 

 

CLOSE VALVE: STATIC TEST 

1. Open cock valve #1 and close cock valve #2.

 

2. Close the plug on the cover. Pressure will be built in the 
main valve cover. Release tube connector slightly to release 
air traps and then close it. The main valve should close.

 

3. Check the valve cover and diaphragm for leaks, tighten 
bolts if necessary.

 

 

START-UP OPERATION 

Note: Ensure upstream pressure exist.

 

1. Close cock valves 1 and 2 to isolate the control system. 
This prevents dirt exposure in the control loop.

 

2. Remove the cover plug on the main valve cover, allowing 
the valve to fully open.

 

3. Open isolation valves.

 

4. Replace the cover plug and close cock valve #2, the main 
valve will close.

 

5. The needle valve #5 is factory set at one to one-and-a-half 
turns.  Turn the needle valve clockwise - to reduce the 
closing rate speed of the main valve - or vice versa.

 

6. Check valve operation by slowly opening / closing cock 
valve #2.

 

 

 

PARTS LIST 
1, 2 

Cock Valve. 

4B 

Stagnation In Line Self Washing Filter. 

Needle Valve. 

22 

2-Way Float Pilot Valve. 