4. Installation
4.1 Delivery check
Check that all has been delivered and that the goods have not been
damaged during transport. If that is not the case, please notify the delivery
company. Transport damages should be reported to the forwarding agency.
4.2 Preparations for installation
Check that the measurements and capacity range of the burner are
compatible with the boiler. The power ratings on the type plate refer to the
min. and max. power of the burner.
4.3 Gas supply
For good operating safety, it is important that the gas supply system is
installed correctly.
Consider the following:
1.
Check that the burner is approved for the gas quality of the installation.
If not, please contact the supplier.
2.
Check that the gas components of the burner are approved for
indicated gas pressure.
3.
The gas supply system should be installed in accordance with current
standards.
4.
Pipe lines should be run so that service on boiler and burner is
facilitated.
5.
Pipe lines should be run so that eventual contaminants cannot come
into contact with the gas components.
6.
Gas discharge system must be installed prior to local regulations.
4.4 Electric connection
Before starting the electric installation, the main switch must be turned off.
If the boiler has a 7-pole and a 4-pole Eurostecker connector, these usually
fit directly to the burner. If not, use the connectors included.
(Refer to connection under Electric equipment)
!
If an electric connection other than the one recommended by Enertech is used, a risk of damage and
injury can arise.
Содержание BG 650
Страница 2: ...2 Bentone...
Страница 19: ...19 Bentone 4 10 Gas nozzle 45 Natural gas Propan Biogas UV detector...
Страница 38: ...38 Bentone 9 2 Wiring diagram LME Design without A3 AGQ Option...
Страница 45: ...172 905 04 2018 02 15 12 EU Declaration of conformity Bentone Gasburners...
Страница 48: ...Enertech AB P O Box 309 SE 341 26 Ljungby www bentone se www bentone com...