Commissioning
56
Mono Power Unit BUM 62, 63, 64
5.94005.12
Baumüller Nürnberg GmbH
6.5
Messages and warnings
6.5.1 Monitoring of the input rectifier
To use the monitoring the +24 V power supply (X99A or X99B) must be available.
Following features are monitored:
- Voltage failure
- Phase failure
- High temperature (overload)
y
Mains monitoring BUM 62
This prevents an internal and external "ready for use" message if a phase is missing in the mains.
y
Mains monitoring BUM 63 / 64
This prevents an internal and external "ready for use" message if a phase is missing in the mains voltage.
y
Phase monitoring BUM 62
The phase failure monitoring function recognizes that a phase is missing in the supply voltage and give
a warning message.
After 10 seconds the error is stored and an internal and external "ready for use" message is prevented.
y
Phase monitoring BUM 63 / 64
This prevents an internal and external "ready for use" message.
y
Temperature monitoring
The temperature of the cooling element is monitored and a warning message is given in case of over-
load, i.e. excess temperature.
After 10 seconds the error is stored and an internal and external "ready for use" message is prevented.
NOTE
After switching on the +24V electronics supply, the operation of the mains monitoring is only saved
when:
- the mains is reported OK for the first time
- the DC link voltage has dropped below 300 V.
Содержание BUM 62
Страница 1: ...E 5 94005 12 Manual Mono Power Unit BUM 62 63 64 ...
Страница 8: ...Safety Notes 8 Mono Power Unit BUM 62 63 64 5 94005 12 Baumüller Nürnberg GmbH ...
Страница 10: ...Technical Data 10 Mono Power Unit BUM 62 63 64 5 94005 12 Baumüller Nürnberg GmbH 2 1 2 Block diagram BUM 62 ...
Страница 14: ...Technical Data 14 Mono Power Unit BUM 62 63 64 5 94005 12 Baumüller Nürnberg GmbH 2 3 Type code ...
Страница 16: ...Transportation Unpacking 16 Mono Power Unit BUM 62 63 64 5 94005 12 Baumüller Nürnberg GmbH ...
Страница 28: ...Installation 28 Mono Power Unit BUM 62 63 64 5 94005 12 Baumüller Nürnberg GmbH ...
Страница 40: ...Installation 40 Mono Power Unit BUM 62 63 64 5 94005 12 Baumüller Nürnberg GmbH 5 5 2 Terminal diagram BUM 63 ...
Страница 41: ...Installation Mono Power Unit BUM 62 63 64 41 Baumüller Nürnberg GmbH 5 94005 12 5 5 3 Terminal diagram BUM 64 ...
Страница 62: ...Commissioning 62 Mono Power Unit BUM 62 63 64 5 94005 12 Baumüller Nürnberg GmbH ...
Страница 66: ...Maintenance 66 Mono Power Unit BUM 62 63 64 5 94005 12 Baumüller Nürnberg GmbH ...
Страница 73: ......