Operation
Power Connection/Disconnection
•
Connecting, disconnecting and grounding are carried out through the plug equipped on the machine. For
safety reasons, DO NOT change this plug into any other type in any situation.
•
For
the control device’s protection, its’ recommended for the operator to supply a fuse with the current rating
and the total length between the fuse and the connecting terminal. Please refer to table below:
Extension Lead Table
Ampere rating
3A
6A
10A
13A
Extension Cable Length
Wire Size (mm
2
)
7.5m
0.75
0.75
1.0
1.25
15m
0.75
0.75
1.0
1.5
22.5m
0.75
0.75
1.0
1.5
30m
0.75
0.75
1.25
1.5
45.5m
0.75
1.25
1.5
2.5
•
Ensure that the Emergency Stop Switch (A, on the left side beside the electrical box) is in the OFF position
before plugging in the cord.
•
Disconnect all tools from power sources before servicing them and when changing their accessories.
Initial Starting
1. Taking all precautions stated, set the HIGH-
LOW range lever to LOW.
2. Insert the electric plug into the socket.
3. Release the Emergency Stop Switch (A) by
pushing down on the red knob slightly and
pushing it up, as indicated by the arrow on
the top of the red knob.
4. Switch on the machine by GENTLY turning
the Variable Speed Control Knob (D)
clockwise. A click will be heard as the motor
power is turned ON, but the spindle will not
rotate until the knob is turning clockwise a
little further. Speed will increase
progressively the further the knob is turned.
5. Run for a total of 5 minutes, during which
you can gradually increase the spindle
speed to its maximum value.
6. Run for at least 2 minutes at this speed
before stopping the machine and
disconnecting it from the mains supply.
7. Ensure that all components are still secure and are working freely and correctly.
8. Ensure that all mountings are secure.