11.4 Recovering from a Lockout
To recover from a lockout condition:
• Follow the recommendation in the fault display (LCD models)
• Follow the recommended steps and checks listed in the
• Perform a system reset
• Cycle the power and perform a system reset, if needed
If these steps do not remedy the lockout condition, contact BERNSTEIN (see
11.5 SCR P Using Automatic Terminal Optimization
Follow these steps for an example configuration that uses the Automatic Terminal Optimization (ATO) feature.
Note:
This procedure is an example only.
1. Click
New Project
to start a new project.
2. Select SCR P
Series
.
3. Define the project settings and click
OK
.
Note:
Make sure that
Disable Automatic Terminal Optimization Feature
checkbox is clear.
The project is created.
4. On the
Equipment
tab, click
below the Safety Controller.
The
Add Equipment
window opens.
5. Add an Emergency Stop button and click
OK
to accept the default settings.
6. Click
.
7. Add an Optical Sensor and click
OK
to accept the default settings.
8. Click
.
9. Add a Gate Switch and click
OK
to accept the default settings.
10. Go to the
Wiring Diagram
tab and notice the terminals that are used.
WARNING: Non-Monitored Resets
If a non-monitored reset (either latch or system reset) is configured
and if all other conditions for a reset
are in place,
a short from the Reset terminal to +24 V will turn On the safety output(s) immediately.
WARNING: Check Before Reset
When performing the system reset operation, it is the user’s responsibility to make sure that all potential
hazards are clear and free of people and unwanted materials (such as tools) that could be exposed to the
hazard.
Failure to follow these instructions could result in serious injury or death.