Installation and Operations Manual 

— Model B3X Series 

 

B&B ARMR

                                                                                                                  

A Division of B&B Roadway and Security Solutions                                                                                           0B30-9001 Revision E2

 

 

 

 

A traffic control gate arm to warn the vehicle operator. This gate arm is 
positioned on the attack side of the barrier and does not open to allow traffic 
until the barrier is fully lowered (stowed), and the gate lowers to block traffic 
before the barrier starts to rise (deploy).   

 

 

Red/amber traffic lights. 

 

 

Infrared safety beams to detect pedestrian traffic or as an additional vehicle 
sensing device. 

2 OPERATION 

2.1  Introduction 

On the automatic version of the B3X, the bollards are moved to the up (or protective) 
position with a single, center mounted hydraulic cylinder.  When the bollards are in the 
raised position, the cylinder is maintained at the system pressure.  The speed of operation 
is determined by the amount of pressurized hydraulic fluid able to pass to the bollards in 
a given amount of time.  This can be controlled by the flow control valves which are 
located in the hydraulic pumping unit. 

2.2  Control 

The automatic B3X Bollard System is controlled by the flow of hydraulic fluid under 
pressure from the HPU to the cylinder.  All control components are connected to the 
HPU.  

2.3  Operating Time 

The operating time for the bollard system is field adjustable at the HPU by varying the 
hydraulic fluid flow from the HPU as required.  Normal operation cycles range from 6-10 
seconds for both up and down.  Emergency fast Operation (EFO) is approximately 1.5-2 
seconds.  The following table illustrates the estimated required flow rates required to 
operate.  These values are to use only for pump sizing and initial set-up.  Actual times 
and pressures will vary in field level tests. 
 
Pressure required to raise the bollard:  250 psi.  (Does not include hose loss) 

Содержание B3 Series

Страница 1: ...D OPERATIONS MANUAL B B ARMR Corporate Office Tech Support 5900 S Lake Forest Drive Suite 230 McKinney TX 75070 Phone 972 385 7899 Toll Free 800 367 0387 Fax 972 385 9887 E mail info bb armr com techs...

Страница 2: ...he world to control access and to protect people equipment and facilities We offer a broad range of vehicle barrier and related security services Turnkey installations Routine barrier preventative mai...

Страница 3: ...f the Occupational Safety and Health Administration OSHA as well as other applicable federal state and local safety regulations and industry standards and procedures For installation outside the Unite...

Страница 4: ...11 Item 22 Proximity Switch 7 1 1 12 Options 7 2 OPERATION 8 2 1 Introduction 8 2 2 Control 8 2 3 Operating Time 8 3 MAINTENANCE 9 3 1 Introduction 9 3 2 Spare Parts 9 3 3 Monthly Inspections 10 3 4 S...

Страница 5: ...ty of drive solutions Automatic HPU Driven Semi automatic Manual and fixed are the standard drive options available The bollard system has been tested to Department of State specifications STD 02 01 T...

Страница 6: ...the cylinder This 10 inch schedule 80 steel cylinder raises and lowers to provide the obstruction during impact When raised the tube protrudes 30 36 inches of grade depending on the model 1 1 3 Tube...

Страница 7: ...8 Guide Strip The acetyl Delrin guide strips ensure the bollard cylinder can move freely with minimum maintenance required 1 1 9 Up Line Hose This hydraulic hose allows hydraulic fluid to be pressuriz...

Страница 8: ...sure The speed of operation is determined by the amount of pressurized hydraulic fluid able to pass to the bollards in a given amount of time This can be controlled by the flow control valves which ar...

Страница 9: ...ed below are recommended Please contact B B ARMR Technical Service Support for assistance with inspections maintenance or repairs if needed Component damage is likely if a vehicle strikes the barrier...

Страница 10: ...f the finish If rust is present wire brush and sand the area then paint with a primer and a matching color Vacuum and clean the pumping unit area Check oil for level pressure and condition in the HPU...

Страница 11: ...er to verify operation and control Check the PLC for normal operation of all logic and functions 3 5 Annual Maintenance Inspections We recommend you perform the following inspections annually Perform...

Страница 12: ...ntrol valve to see if problem is mechanical or electrical Q If mechanical 5 Check for binding between moving plate and frame Check connection of linkage between frame and plate Check for foreign debri...

Страница 13: ...vely hot 1 Check that the pressure relief valve is closed fully clockwise 2 Check that the pressure switch is adjusted to shut the motor off before 1900 PSI 3 Check for correct voltages Bollard moves...

Страница 14: ...ot limited to unauthorized repairs improper installation installation not performed by BBRSS authorized personnel incoming supply power is outside the tolerance for the product failure to perform manu...

Отзывы: