Commissioning
You must clean the unit after delivery.
Remove all cardboard, protective paper layers, film and adhesive tape.
Clean surfaces with suitable cleaning agents.
ª
Chapter "Cleaning and care" on page 40
9
Unit has reached room temperature and is dry.
9
Unit and mains plug have no known defects or visible damage.
9
Protective films removed.
Caution!
Wrong mains voltage, wrong mains frequency!
The unit electrical system may suffer damage if the unit is not designed for the available mains
voltage or frequency.
Before connecting, make sure that the mains voltage and frequency on the rating plate
correspond with those for the mains socket outlet.
During the initial start-up, the insulation material becomes hot and may cause an unpleasant
odour.
B.PRO recommends:
Heat the unit compartments and bain-marie wells for approx. 2 hours before first use.
Prepare each bain-marie well accordingly.
ª
Chapter "Wet loading bain-marie wells (recommended)" on page 31
Cover the bain-marie wells with a suitable lid (such as a GN lid) while they are first being
heated up in order to save energy.
9
Unit doors closed.
Initial start-up
Make sure that no protective film is left inside the unit compartments or on the exterior
of the unit.
Make sure that there are no heat-sensitive objects in the bain-marie wells or unit
compartments.
Connect the mains plug to the socket outlet.
Switch on all unit compartments and the bain-marie wells at the corresponding on/off switch.
The operation indicator LED will illuminate.
Set rotary knob to the highest level.
Heat the unit compartments and bain-marie wells for approx. 2 hours.
Switch off all unit compartments and the bain-marie wells at the corresponding on/off switch.
The operation indicator LED will go out.
Ventilate the unit compartments.
Carrying out initial
cleaning
Prerequisites for
operation
Initial start-up