IMPORTANT SAFETY INFORMATION LISTED ON REVERSE
READ, FOLLOW, AND SAVE ALL SAFETY AND INSTALLATION INSTRUCTIONS
Housing Installation
7. Per DIG-IT Guide, backfill the gap between the
bottom of housing and bottom of hole with sand for
drainage.
8.
For soil installation:
Fill and tamp soil to the
appropriate height leaving room for sod, pavers,
etc. to be level with the top of the temporary cover.
Soil installation is not drive-over rated.
OPTIONAL GROUT MASK INSTALLATION
(IF ORDERED)
7. Fill partway, then place grout mask around housing,
centered at faceplate. Insert stakes through stability
flange. Top of grout mask should be flush with
grade.
1. Connect branch conduit connectors (not included)
to the junction box using either the threaded
conduit entries on the bottom of the junction box or
through holes drilled into the sides of the junction
box.
Recommend 7/8” drill bit for side installation.
2.
Place housing in hole. Align junction box in the
path of the conduit trench.
3. Insert four (4) pieces of ½” EMT conduit through
the stability flange. Hammer into substrate until
secure.
Leave sufficient clearance to elevate housing to
finished grade.
4. Raise housing on EMT so housing is flush with
finished grade. Use a level to aid in housing
installation.
5. When housing is level, tighten screws on stability
flange to secure housing to EMT. Remove excess
EMT as needed.
6. Pull primary branch circuit wiring into junction
box.
Flush with finished grade
Standard Instructions
HP2
INTEGRAL TRANSFORMER - STANDARD MR16 & PAR36/AR111
RELEASE DATE
08/28/2023
40429 Brickyard Drive • Madera, CA 93636 • USA
559.438.5800 • FAX 559.438.5900
www.bklighting.com • [email protected]
B-K LIGHTING
REFERENCE NUMBER
INS-2858-00
Threaded Entry
Side Flats