2
Aviat Networks
Chapter 5. Eclipse Edge Commissioning and Troubleshooting
Table 5-1.
Typical Commissioning Check Process
Step Description
Procedure
1
Physical installation
inspection
A physical check prior to antenna alignment and node
configuration to ensure that the physical installation is
complete and correct.
2
Antenna alignment
confirmation
An antenna alignment procedure is detailed in
. Recorded RSLs should be
within 2.5 dB of calculated RSLs.
3
Configuration
confirmation
A check, using Portal, to ensure that terminal configurations
are complete and correct and that:
• The link is operating error-free.
• All relevant alarms are extinguished.
• Link performance data is as expected.
• IP addressing and routing is set correctly, which can be
confirmed from ProVision, where installed.
4
Commissioning tests
Tests designed to confirm correct link operation. Refer to
Eclipse Edge Commissioning Tests on page 3
5
Capturing as-built data
Recording all relevant installation and performance data for
future reference. Refer to
Commissioning Records for Edge
.
6
Final inspection and
sign-off
Completion of ‘paperwork’ recording installation hand-over for
operational use, and/or any remedial action needed to
complete an installation. Refer to
Содержание ECLIPSE EDGE
Страница 1: ...ECLIPSE EDGE Version 5 USER MANUAL 260 668080 001...
Страница 2: ......
Страница 3: ...Eclipse Edge Microwave Radio System User Manual Software Version 5 0 March 2013...
Страница 14: ...16 Aviat Networks INDEX...
Страница 18: ......
Страница 26: ...8 Aviat Networks Chapter 1 Health and Safety...
Страница 236: ...8 Aviat Networks W warnings safety 1 2 warranty i ii WEEE directive i v X XP4 NMS compatibility for Edge 4 71...
Страница 272: ...36 Aviat Networks Chapter 3 Eclipse Edge Installation...
Страница 273: ......
Страница 274: ...260 668080 001 WWW AVIATNETWORKS COM...