Connecting the media gateway to the main distribution frame
Installing the Avaya S8700 Media Server with an Avaya G650 Media Gateway
151
December 2003
Cable routing guidelines
Figure 54, Cable routing to top terminal blocks,
on page 151 and
Figure 55, Cable routing to bottom
terminal blocks,
on page 152 show typical cable routing from the media gateway to the top and bottom of
the MDF, respectively.
Figure 54: Cable routing to top terminal blocks
Figure notes
1
Main Distribution Frame
2
AC Power Cord (AC-powered media
gateways only)
3
Cable Slack Manager Number 1
4
Trunk/Auxiliary Field
5
Station Distribution Field
6
Cable Slack Manager Number 2
7
Cable Slack Manager Number 3
8
Media Gateway(s)
9
To Building Cables
10
10 AWG (#25) (6 square millimeters)
Wire to Coupled Bonding Conductor
r758424b MMR 052996