3.3
Fitting the cover
After connection:
.
Insert the socket carrier (51.0) into the plug cover (50.0) and fasten it with
screws (51.01).
.
Clean sealing faces at the plug cover and the housing.
.
Check whether O-ring is in good condition.
.
Apply a thin film of non-acidic grease (e.g. Vaseline) to the sealing faces.
.
Replace plug cover (50.0) and fasten bolts (50.01) evenly crosswise.
.
Fasten cable glands with the specified torque to ensure the required
enclosure protection.
6
Actuator controls AUMA MATIC AM/ AMExB/ AMExC
Profibus DP
Short instructions bus connection
Figure B-3: Connection board (for overvoltage protection)
from previous / to next
Profibus DP device
channel 1
S1
Bus termination
channel 1
S2
Bus termination
channel 2
x1
x2
X1
1
2
3
4
Figure B-4: Connection for overvoltage protection
Profibus
cable
AUMA
labelling at the
connection
SUB-D 9 plug pin
(for other
Profibus devices)
Colour
A
N/A
8
green
B
P/B
3
red
Table 3: Assignment of Profibus cable