Equipment Room Hardware And Cabling Installation
Routing Cables From Cabinet to Cross-Connect Field
The following guidelines should be followed when routing cables from
the cabinet to the cross-connect field.
●
●
●
When cable routing is to the top/bottom of the cross-connect
field, each port cable is connected at the cabinet and then routed
along the front trough of the cable slack manager to the
connecting/terminal block where the cable is to be terminated.
Enough slack must be left at the cabinet end of the cable to allow
for proper dressing of the cables (Figure 3-50).
Route the cable from the cabinet to the wall. Place the cable
beside one of the rows of columns in the cable slack manager
(see Note).
Note: Retainers mounted on the columns keep the cable
from protruding above the top of the base of the cable slack
manager.
●
●
●
●
Determine the length of the cable required to reach from the cable
slack manager to the assigned connecting/terminal block.
The cable must be supported on the wall using D rings.
Cable slack is stored by coiling the cable around the columns in
the cable slack manager. The first run should always go across
the full length of the five columns in the cable slack manager.
Connect the cable to the assigned connecting/terminal block.
3-73
Содержание System 75
Страница 1: ...AT T AT T System 75 and System 75 XE Wiring...
Страница 2: ...AT T AT T System 75 and System 75 XE Wiring 555 200 111 Issue 2 August 1989...
Страница 16: ...System Wiring Figure 1 2 System Uniform Wiring Plan 1 7...
Страница 17: ...CHAPTER 1 INTRODUCTION Figure 1 3 Sample Uniform Wiring Installation 1 8...
Страница 29: ...CHAPTER 2 HARDWARE 66 110 Type Figure 2 1 Block Diagram of System 75 or 75 XE Installation 2 2...
Страница 35: ...CHAPTER 2 HARDWARE 66 110 Type Figure 2 4 110A Type 100 Pair Terminal Block 2 8...
Страница 36: ...110 Type Hardware Description Figure 2 5 110A Type 300 Pair Terminal Block 2 9...
Страница 98: ...Typical System Equipment Room Floor Plans 3 15...
Страница 143: ...CHAPTER 3 EQUIPMENT ROOM DESIGN 3 60...
Страница 144: ...Equipment Room Hardware And Cabling Installation 3 61...
Страница 162: ...Equipment Room Hardware And Cabling Installation 3 79...
Страница 163: ...Equipment Room Hardware And Cabling Installation 3 80...
Страница 197: ...Tables Table 4 A Recommended Protectors 4 42 v...
Страница 203: ...CHAPTER 4 STATION WIRING Figure 4 4 3 Pair to 4 Pair Wiring Labeling From Equipment Room to Information Outlet 4 6...
Страница 205: ...CHAPTER 4 STATION WIRING Figure 4 5 4 Pair Station Wiring Labeling From Equipment Room to Information Outlet 4 8...
Страница 212: ...Adjunct Powering 4 15...
Страница 214: ...Adjunct Powering 4 17...
Страница 216: ...Patch Cord Jumper Installation And Administration 4 19...
Страница 241: ...CHAPTER 4 STATION WIRING 4 44...
Страница 244: ...Miscellaneous Wiring Installation 4 47...
Страница 246: ...Miscellaneous Wiring Installation 4 49...
Страница 252: ...Miscellaneous Wiring Installation 4 55...
Страница 254: ...Miscellaneous Wiring Installation 4 57...
Страница 277: ...CHAPTER 5 AUXILIARY EQUIPMENT INSTALLATION Figure 5 1 Connections for Loudspeaker Paging and Music on Hold 5 4...
Страница 314: ...CHAPTER 5 AUXILIARY EQUIPMENT INSTALLATION 5 41...
Страница 324: ...CHAPTER 5 AUXILIARY EQUIPMENT INSTALLATION 5 51...