Asetek InRackCDU Installation, Operation & Maintenance Guide 15
6
System Startup
6.1
Preparation of floor for InRackCDU with for facility tubes connection in the bottom
The flooring for InRackCDU with facility connection from the bottom must be prepared with a 100x150mm
opening for routing of the facility hoses from underneath the floor to the InRackCDU inside the rack as
below example.
6.2
Connecting the InRackCDU System to Facilities Water
The facility water line should be prepared with male and female camlock connectors as shown below.
Water flows from the male camlock into the female camlock. Connect the cam locks by bringing the two
ends together and then pull back the handles on the female connector as shown in the second picture.
150mm
100mm