CXCM2 Cordex Controller Replacement Procedure 

 
 
Summary 
 

This procedure describes the process of removing and replacing the CXCM2 modular controller from the 
1.8kW shelf after inhibiting the low voltage disconnect and preserving any custom settings. 
Note: Any system software changes made on site would need to be transferred, by backing up the 
configuration as shown in step 1 and 2. The replacement CXCM2 unit will ship with with the factory original 
configuration specified for your setup. 

 
Tools/Information Required 
 

• Voltmeter 
• Ethernet crossover cable 
• Philips screw driver 

 
Preparing for Removal of CXCM2 
 

1.  Save CXC configuration file if necessary (see software manual). 
 
 

 

 
 
 
 
 
 
 

Содержание Cordex CXCM2

Страница 1: ...custom settings Note Any system software changes made on site would need to be transferred by backing up the configuration as shown in step 1 and 2 The replacement CXCM2 unit will ship with with the factory original configuration specified for your setup Tools Information Required Voltmeter Ethernet crossover cable Philips screw driver Preparing for Removal of CXCM2 1 Save CXC configuration file i...

Страница 2: ...o the controller is removed Remove the DB connectors from I O Terminal Block 3 Standard Customer Connections on the I O terminal block for the 1 8kW Shelf P3 JUMPER SETTINGS FOR LVD CONTROL INHIBIT FUNCTION SHORT PINS 1 AND 2 IF LVD IS CONTROLLED ON K1 NC CONTACTS TO MAINTAIN OPERATION SHORT PINS 2 AND 3 IF LVD IS CONTROLLED ON K1 NO CONTACTS TO MAINTAIN OPERATION ...

Страница 3: ...3 300A UDC Connections Bypass system LVD by setting override switch on UDC to OVERRIDE Remove DB Connectors from the I O Board Removal of CXCM2 4 Remove signal wires via DB connectors from CXC ...

Страница 4: ...he bottom of the faceplate to secure to shelf CAUTION Do not push on the LCD 7 Connect the DB Connectors at CXCM2 first before connecting back the other end to the UDC I O Board 8 Upload original configuration file to restore setup 9 Use a meter to verify calibration of the system voltage temperature and current shunt Recalibrate if needed following attached calibration procedure 10 Remove LVD byp...

Отзывы: