Figure. 5.4.10 - 210. Extending a logical input pulse.
5.5 Monitoring functions
5.5.1 Current transformer supervision
The current transformer supervision function (abbreviated CTS in this document) is used for monitoring
the CTs as well as the wirings between the device and the CT inputs for malfunctions and wire breaks.
An open CT circuit can generate dangerously high voltages into the CT secondary side, and
cause unintended activations of current balance monitoring functions.
Figure. 5.5.1 - 211. Secondary circuit fault in phase L1 wiring.
A
AQ
Q-G215
-G215
Instruction manual
Version: 2.04
335
Содержание AQ-G215
Страница 1: ...AQ G215 Generator protection IED Instruction manual ...
Страница 399: ...Figure 7 4 241 Example block scheme A AQ Q G215 G215 Instruction manual Version 2 04 398 ...
Страница 421: ...Figure 8 14 264 Panel cutout dimensions and device spacing A AQ Q G215 G215 Instruction manual Version 2 04 420 ...
Страница 456: ...10 Ordering information A AQ Q G215 G215 Instruction manual Version 2 04 455 ...