Page 21
BK 680 Specific
ECOBOILER Cassette Installation Guide
8. Final check list and commissioning the stove
Before handing over the installation to the customer it is a requirement under
Document J (of the Building Regulations for England & Wales) that the
appliance is lit and the functioning of the chimney system is checked for
satisfactory operation. The functioning of the hot water and heating system
should be fully checked.
Please record the checks in the table below :
Operate the heating system and set the pump head.
Balance the radiators.
Re-vent and ensure there are no air leaks.
Check all joints & seals.
Clean the outside of the appliance to prevent any stains
from becoming burnt on.
Check the flue draught which should read 1 –2 mm or
0.1—0.2 mbar.
For a registered competent persons scheme please
complete a Certificate Of Compliance, which is used for
checking and reporting the installation as imposed by
the Government.
Explain the controls and operation of the appliance to
the customer.
Ensure a Carbon Monoxide alarm is fitted. This must be
between 1 to 3 metres of the appliance and
approximately 150mm below the ceiling level.
A fireguard conforming to BS 8423:2002 should be
used in the presence of children and old or infirm
people.
Explain to the customer, that when lighting a boiler
stove, condensation may form on cold parts of the stove
and drip off of it during ignition. This is normal and not
an indication of a leak.