background image

2022/07/14

Rev3.0

Quick Installation Guide

1

QT2D Microinverter Quick Installation Guide

Step 1. Verify that grid voltage matches microinverter rating
Step 2. Y3 AC Bus Cable distribution

a. Each connector drop of the AC Bus cable matches the position of the microinverter.

b. One end of the AC bus cable is used to access the junction box into the power grid.

c.

Wire the conductors of the AC bus:L1 - BROWN; L2 - BLACK;L3 - GRAY(European Standard);or L1 -

BLACK; L2 - RED

L3 - BLUE(American Standard).

NOTE: Wiring color code can be different according to the local regulation. Check all the wires of the

installation before connecting to the AC bus to be sure they match. Wrong cabling can damage irreparably

the microinverters: such damage is not covered by the warranty.

Step 3. Attach the APsystems Microinverters to the Racking

NOTE: Install the microinverters (including DC and AC connectors) under the PV modules to avoid direct

exposure to rain, UV or other harmful weather events. Allow a minimum of 1.5 cm (3/4

’’

) below and above

the casing of the microinverter to allow proper air flow. The racking must be properly grounded as per local

electrical code.

Step 4. Ground the system

Step 5. Connect the APsystems microinverter to AC bus cable

Step 6. Install a Bus Cable End Cap at the end of AC bus cable

Step 7. Connect APsystems Microinverters to the PV Modules

a

b

c

Please scan the QR code to get

mobile app and more support to

help the installation.

ATTENTION: Do NOT carry the microinverter by the AC cable. This may cause the AC cable to partially or

fully disconnect from the unit, resulting in no or poor operation.

a. Mark the location of the microinverter on the rack, with respect

to the PV module junction box or any other obstructions.

b. Mount one microinverter at each of these locations using

hardware recommended by your module racking vendor.

M8 (Not supplied by

Apsystems)

grounding washer

Warning injure hand

2. By grounding copper wire.

Fix the grounding copper wire by the grounding lug.

There're 2 ways to ground the QT2D series microinverters.

1. By grounding washer attached.

After the microinverters and racking are reliably installed, the

microinverter's grounding washer can connect to the racking to

ensure proper earthing.

grounding

lug

Best Practice: Use the Bus Cable Unlock Tool of AC Bus to

disconnect the connectors.

NOTE: AC connector interface as from left to right.

NOTE: Cover any unused connectors with Bus Cable Y-CONN

Cap to protect the unused connectors.

Insert the microinverter AC connector into the trunk cable

connector. Make sure to hear the “click” as a proof of robust

connection.

Click

L3

L2

L1

3.3N·m

NOTE: When plugging in the DC cables, the microinverter should immediately blink green ten times. This will

happen as soon as the DC cables are plugged in and will show that the microinverter is functioning correctly.

This entire check function will start and end within 10 seconds of plugging in the unit, so pay careful

attention to these lights when connecting the DC cables.
WARNING! Double check to make sure all of the AC and DC wiring has been correctly installed. Ensure that

none of the AC and/or DC wires are pinched or damaged. Make sure that all of the junction boxes are

properly closed.

WARNING! Each pv panel must be carefully connected to the same channel.

Never split positive and negative cables into two different channels, otherwise the inverter will be damaged

and warranty will not apply.

Отзывы: