Four post parking lift AM-FPL9
a minimum of 12” thickness with
steel or fiber mesh. New
concrete must be adequately cured by at least 30 days
minimum.
ANCHORING GUIDELINES
⚫
Please carefully remove all the parts from the package.
⚫
Use a concrete rotary hammer drill with 3/4” drill bit. Do not
use excessively worn or incorrectly sharpened drill bits.
⚫
Keep the drill in a vertical position when drilling. Do not apply
excessive pressure and let the drill do the work. Try to lift the
drill up sporadically and clean residue in the hole. Power blow
dust from the hole for better holding.
⚫
Drill the holes 1.25" deeper than the length of the anchor bolts.
Try to drill through the concrete so that when you move the
lift to a new location, you may hammer down the anchor bolts
instead of cutting them off.
⚫
Assemble the washers and nuts onto the anchor bolts. Thread
the nuts onto the anchor bolts where the tops of the nuts are
just above the top of the bolts, as shown in figure below.
Using a hammer, carefully tap the anchor bolts into the
concrete until the washer rests against the baseplate. Do not
damage the nuts or threads. Try not to use an impact wrench
to tighten the nut. Tighten the nut two or three turns after the
concrete is cured (30-day minimum cure). In case where the
concrete is very hard, tighten only one or two turns.
Содержание AM-FPL9
Страница 1: ...PLEASE READ THE PRODUCT MANUAL ENTIRELY BEFORE INSTALLING OR OPERATING THE LIFT ...
Страница 9: ...Four post parking lift AM FPL9 8 LIFT COMPONENTS ...
Страница 10: ...Four post parking lift AM FPL9 9 LIFT DIMENSIONS ...
Страница 24: ...23 Four post parking lift AM FPL9 5EXPLODED DRAWING ...
Страница 25: ...24 Four post parking lift AM FPL9 ...
Страница 26: ...25 Four post parking lift AM FPL9 ...
Страница 27: ...26 Four post parking lift AM FPL9 MAINTENANCE LOG ...
Страница 28: ...27 Four post parking lift AM FPL9 ...