4
Amphenol Network Solutions
All rights reserved. 12.18.19 139688-3
509.926.6000 – amphenol-ns.com
100A Dual-Feed
Breaker Panel
1.3 Installation
NOTE:
Panel brackets provide either flush or extended EIA or WECO mounting in a 19-in. or 23-in. rack.
The panel is configured at the factory for flush mounting in a 19-in. rack.
Procedure steps:
1. If necessary, remove three screws and reposition/re-align
brackets on sides of distribution panel, as shown in Figure 2.
2. Locate an unused rack position and mount panel using the
four screws and lockwashers provided, as shown in Figure 3.
(It’s best to mount the panel as high as possible on the rack.)
Tighten screws to 35 in.-lb (4.29 N
•
m).
WARNING! Failure to properly ground this equipment can create hazardous conditions to
installation personnel and to the equipment.
ALERT! Only use components and crimping tools approved by agencies or certifying bodies
recognized in your country or region such as Underwriter’s Laboratories (UL), TUV, etc.
Torque #8 screws to
15 in.-lbs [1.7 N•m]
Mounting
Bracket
3-in. Offset
Position
4-in. Offset
Position
Flush Position
Figure 2 – Bracket Orientation
Figure 3 – Rack Mounting