Amiad Water Systems - ADI-X IOM 910101-001180 / 06.2021
76
5.8
Chaining ADI-X Controllers
ADI-X controller can be set as primary controller that controls up to 3 secondary ADI-X controllers.
Primary controller flushing trigger is performed by the secondary controllers. All flush settings are
set on each secondary controller separately.
To chain controllers:
1.
Connect each secondary controller to the primary controller using "Ext" A and B contacts.
Figure 68: ADI-X controllers chaining
2.
Set the primary controller Operation mode to "Primary" and select the number of the
secondary controllers (for primary controller settings - see 5.3).
3.
Set the secondary controllers Operation mode to "Secondary" (see 5.3).
Primary
Secondary 1
Secondary 2
Secondary 3