hypercharger - Operation Instructions and Installation Guide
Version 1-1C
Page 28 of 57
4
Mechanical
installation
All rights reserved. The reproduction of this document, also partially, is allowed only with authorization by alpitronic s.r.l.
Figure 23:
Distances between base plate and outer dimensions of charging station on the concrete
foundation (HYC_225, HYC_300) (front/top view)
4.2. Adaptor
A hypercharger adaptor is only needed if a universal foundation (e.g. UNIMI QC) is used.
In this case, the adaptor is screwed to the foundation with screws on standard positions
(defined by the used foundation) and the hypercharger-base is screwed together with the
adaptor (see the following chapter).
To realize the mechanical mounting of the hypercharger on the concrete foundation, the
foundation must be equipped with minimal four M12 metric screw threads, in the following
positions:
Suitable washers are to be provide. To realize the mains power-supply from the ground,
the cable outlets in the foundation need to be in the middle of the hypercharger-base /
Mounting threads of the foundation:
4.3. hypercharger-base
The hypercharger-base needs a gap of 50mm from the ground level facilitate the
connection of the mains-side supply cables.
The following figure shows the hypercharger-base for the HYC_075 and the HYC_150: