8. System Startup
After completing the system installation and power system wiring, perform the following startup and test procedure
to ensure proper operation.
1. Visually inspect the installation thoroughly.
2. Verify:
x
AC input power is off.
x
Batteries are disconnected.
x
All breakers are off and no GMT fuses installed if any loads are connected.
x
All power modules are removed from the shelf.
3. Triple-check the polarity of all connections.
4. Install one rectifier module into the front left-most position using the side of the shelf as a guide.
x
Place the rectifier module on the shelf.
x
Lift the handle and slide the module into the rear connector inside the shelf.
x
Apply pressure on the module front panel to engage the rear connector in the shelf receptacle.
x
Flip the handle down to lock the module into place.
5. Verify that the AC input voltage is correct and that the breaker switch for the corresponding feeder breaker is
ON.
x
The power module OK LED will illuminate after a preset start delay.
6. Test the functionality of various module alarms and controls using the controller's LCD screen or web interface.
7. Verify the correct battery polarity using a voltmeter. Ensure that no cells or batteries are reversed.
8. Connect the batteries to the output of the system.
9. Install the remaining power modules.
10. Configure the battery parameters according to the battery manufacturers recommendations. See the CXC HP
software manual for detailed instructions on how to configure the batteries.
11. From the
Power System> System Functions> Battery Maintenance> Equalize
menu of the controller, set the
float and equalize voltage to the levels specified by the battery manufacturer.
12. Use the controller to test the functionality of various module alarms and controls especially the battery breaker
alarm test. Verify alarms are transmitted to site monitor.
13. Perform a load test with the system using a resistive load box.
14. Enable the temperature compensation feature in the
Power System> System Functions> Temperature
Compensation
menu. Program the settings for slope and breakpoints (upper and lower) with respect to the
specific batteries used.