Chapter 11: Verifying the Hardware Operations of the Chassis
232
Section II: Installing the Chassis
Using the LEDs to Verify the Chassis
After powering on the chassis for the first time and waiting a minimum of
three minutes for the line and controller cards to complete the initialization
process, check the operational status of the various hardware
components by examining the LEDs, as explained in this procedure:
1. Check the LEDs on the power supplies:
AT-SBxPWRSYS1, AT-SBxPWRSYS2, and AT-SBxPWRPOE1
AC Power Supplies: The power supplies are operating properly
when the AC and DC LEDs are solid green and Fault LEDs are off.
If there is a problem, refer to “AT-SBxPWRSYS1, AT-
SBxPWRSYS2, or AT-SBxPWRPOE1 AC Power Supplies” on
page 238 for troubleshooting suggestions.
AT-SBxPWRSYS1 DC Power Supply: The power supply is
operating properly when the DC IN and DC OUT LEDs are solid
green and the Fault LED is off. If there is a problem, refer to “AT-
SBxPWRSYS1 DC Power Supply” on page 240 for
troubleshooting suggestions.
2. Check the Power LED on the AT-SBxFAN06 module. The module is
operating normally when the LED is solid green. If the LED is off, the
fan module has a problem or failed. Power off the chassis and contact
your Allied Telesis representative for assistance. Do not operate the
chassis without a fully operational fan unit.
3. If the chassis has one controller card, check the CFC LED on the card.
It should be solid green. If the LED is flashing green, the card is still
initializing its AlliedWare Plus Operating System. Wait another minute
and check the LED again. If the LED is still flashing green, the card
may have encountered a problem that prevents it from completing the
initialization process. Power off the chassis and replace the controller
card.
Note
If all the LEDs on the controller card are off, they may have been
turned off. Try pressing the eco-friendly button on the card to turn
them on.
4. If the chassis has two controller cards, check the CFC LEDs on both
cards. The cards are operating correctly when the LEDs are solid
green on one card and solid amber on the other. If both LEDs are
flashing green, the controller cards are still completing the initialization
process. If the LEDs do not change to solid green and amber after
another minute, the cards may have encountered a problem that
Содержание AT-SB*81CFC960
Страница 20: ...20...
Страница 34: ...Chapter 1 Chassis and Power Supplies 34 Section I Hardware Overview...
Страница 94: ...Chapter 3 AT SBx81CFC960 Controller Fabric Card 94 Section I Hardware Overview...
Страница 96: ...96...
Страница 142: ...Chapter 6 Installing the Power Supplies 142 Section II Installing the Chassis...
Страница 166: ...Chapter 7 Installing the AT SBx81CFC960 Controller and Ethernet Line Cards 166 Section II Installing the Chassis...
Страница 230: ...Chapter 10 Powering On the Chassis 230 Section II Installing the Chassis...
Страница 254: ...Chapter 12 Troubleshooting 254 Section II Installing the Chassis...
Страница 298: ...Chapter 14 Upgrading the Controller Fabric Card 298 Section II Installing the Chassis...
Страница 300: ...300...
Страница 314: ...Chapter 15 VCStack Plus Overview 314 Section III Building a Stack with VCStack Plus...
Страница 356: ...Appendix A Technical Specifications 356...