Rockwell Automation Publication 1756-RM093J-EN-P - April 2018
53
Safety Application Development
Chapter 6
Commissioning Life Cycle
The flowchart below shows the steps required for commissioning a GuardLogix®
system. The items in bold text are explained in the following sections.
Figure 15 - Commission the System
Specify the Control Function
Create Project
Online
Create Project
Offline
Attach to Controller and Download
Test the Application Program
Generate Safety Task Signature
Confirm the Project
Record Safety Task Signature
Project Verification Test
Safety Validation (Independent Review)
Lock the Controller / End
Make required
modifications
Delete Safety Task Signature
Tests
Passed?
Project
Valid?
No
Yes
No
Yes
Содержание 1756-L61S ControlLogix 5561S
Страница 10: ...10 Rockwell Automation Publication 1756 RM093J EN P April 2018 Preface Notes...
Страница 64: ...64 Rockwell Automation Publication 1756 RM093J EN P April 2018 Chapter 6 Safety Application Development Notes...
Страница 70: ...70 Rockwell Automation Publication 1756 RM093J EN P April 2018 Chapter 7 Monitor Status and Handle Faults Notes...
Страница 114: ...114 Rockwell Automation Publication 1756 RM093J EN P April 2018 Index Notes...
Страница 115: ......