Aeon Labs HEM Installation Guide
|
v1.3
1
Aeon Labs HEM
|
Installation Guide
Aeon Labs Home Energy Monitor
Step 1: Connecting Home Energy Monitor to the AC Mains
1)
Important: Turn the main breaker off and open the main
circuit box panel.
2)
Clip clamps of the meter around the incoming electricity
cable that connect to the main circuit breaker.
Important:
HEM G2 have directionality on the clamps.
Please make sure
that the direction of the current is going from K to L on both
clamps.
Both clamps need to be consistent in the direction
of the current (from K to L).
3)
Connect the clamp to the meter using a Clamp Connector (1).
4)
Affix one of the AC Power exposed wires into a neutral bus
terminal and the other exposed wire into a live terminal
coming from the main circuit breaker.
Step 2: Placing the Home Energy Meter
It is now time to place the main body of the Home Energy Meter.
Inside the meter is a radio antenna used for communications, and
this must be taken into consideration when selecting a location for
the meter.
If the circuit box is made of metal, it is recommended that the main
body of the meter be affixed outside the circuit box. The Home
Energy Meter G2 has been weatherized to the international IP44
standard so that it is resistant to rain and snow when placed
vertically with the wires protruding from the bottom of the unit.
1)
Slip open the backing plate from the back of your meter
2)
Affix the plate to the selected wall space using the provided
screws
3)
Attach your meter to the backing plate.
4)
Replace the main circuit box panel.
5)
Turn the main breaker back on.