ROUTED – PICKET & HAWTHORNE FENCE INSTALLATION INSTRUCTIONS 

 
These instructions are to be used as general 
guidelines for the installation of your vinyl fence 
under normal installation conditions. Local 
conditions may exist which may require changes 
in the recommended methods of installation 
noted in these instructions such as extreme 
weather, bad soil conditions such as expansive 
soil or poorly compacted soil, extreme winds or 
heat, etc. 
 
1.  Before you begin, familiarize yourself with 

the installation instructions. 

2.  Tools Required for Installation: 

a)  Measuring tape 
b)  Wood or Metal Stakes 
c)  Post-hole digger / auger 
d)  Post-mix concrete 
e)  String 
f)  Hammer 
g)  Shovel 
h)  Spray paint 
i)  Wheelbarrow 
j)  Level 
k)  Duct tape to seal rail ends 
l)  Saw 
m)  Drill 
n)  Wrenches (adjust gate) 

 

3.  KNOW WHAT’S BELOW BEFORE YOU 

DIG! Most areas have a call center that you 
can call to have the utilities located prior to 
digging. Calling your local utility company is 
the easiest way to determine who to call. It 
is important to note that most utility 
companies will not locate and mark private 
utility lines that were installed by 
homeowners or contractors. Locating utility 
lines prior to digging may not only save your 
life, it may also release you of liability in 
many cases if a line is hit during installation 
that should have been located but was not. 
Prior to digging the holes, you should be 
prepared with emergency numbers to call in 
the event that a utility line is damaged. 
 

4.  FENCE LAYOUT: 

 

When you purchased the fence you likely drew a 
layout and determined the amount of fencing 

you needed. It is very helpful to draw the layout 
of the fence prior to purchasing and installing 
your vinyl fence. 
 

 

Once you have drawn the fence layout (sample 
above) and received your product, it is time to 
mark the locations to dig the holes for the posts. 
 
To start, hammer a stake at each corner and 
end location of your fence. Pull a string line 
between the end and corner posts. This string 
line represents where the center of your fence 
will be. Many people offset the string line at this 
time so that it represents the edge of the fence 
line; this will save an extra step when you begin 
setting the posts (see Figure 1.1). 
 
Determine gate post locations and set stakes at 
these locations. Once you have pulled the string 
line tight you can now mark the center of each 
post along the string line. 
 
Mark the post hole location by beginning at one 
end of the fence and marking the center to 
center measurement of each post (your center 
to center measurement can be found on the 
specification sheet of the style fence 
purchased). For example, if you have a 96½” on 
center section, you will measure from the center 
of your first post 96½” and mark the ground with 
upside down marking paint. Continue marking 
down the string line until you get to the end post. 
See (Figure 1.1). 
 
 
 