CR12 - CR165 50/60Hz
CONDENSERS
Commissioning Procedure
GENERAL
To be read in conjunction with the commissioning sheets provided.
CAUTION
Please ensure all documents have been completed correctly and return to Airedale Technical Support immediately to
validate warranty.
Pre Commissioning Checklist
CAUTION
ALL work MUST be carried out by technically trained competent personnel.
The equipment contains live electrical and moving parts, ISOLATE prior to maintenance or repair work.
CAUTION
The following commissioning information is based on a complete matched Airedale system using R410A.
Start-Up
Switch on the power supply to the condenser and switch the isolator to the on position.
The fan motor starts automatically when the refrigerant condensing pressure reaches the pre-set value of the pressure
regulator (factory set). Therefore to check operation of the condenser the indoor unit to which it is linked must be
running. Refer to Control Device Adjustment.
General
1
The unit condition is satisfactory.
2
All pipework is complete and insulated where necessary.
3
All fans are able to rotate freely.
Electrical
1
All electrical connections (both mains and control) are properly terminated.
2
The power supply is of the correct voltage and frequency.
3
External fuses/circuit breakers are of the correct rating.
4
The units are properly earthed in accordance with current regulations.
5
All pipework is earth bonded as required.
Refrigeration
1
Check for the presence of a refrigerant charge in the condenser.
2
The system has been evacuated correctly.
36
Condenser Technical Manual 6666879 V1.2.0_05_2013