Installing the platform
Installing the 96AM Wash Station and Pump Module
16
AssayMAP Bravo Platform Installation Guide
Routing the tubing
Refer to the preceding table and figure, and use the following procedure to
route the wash station tubing.
To route the tubing:
1
Prepare two 3- way (Y- connector) tubing assemblies and connect them to
the wash station, as follows:
a
Cut three 10.16- cm (4- inch) lengths of the 1/4- inch tubing, and place
one length on each of the three barbed ends of a 1/4- inch 3- way
connector (
a
).
b
Attach the two free ends of the prepared 3- way tubing assembly to the
wash station outlet ports, as the following figure (
b
) shows.
c
Repeat step a to create a second 3- way tubing assembly, and attach it
to the wash station inlet ports (
c
). Secure the tubes on the inlet ports
using tubing clamps.
2
For the top pump, prepare an approximately 20.32- to 25.4- cm (8- to
10- inch) length of 1/4- inch tubing, and insert quick- connect fittings on
both ends.
3
Place this tubing assembly within the top pump head, as follows:
a
Lift up the flip- top cover on the pump head so that it is fully open.
a
b
c
00306
Содержание AssayMAP Bravo
Страница 1: ...AssayMAP Bravo Platform Installation Guide Original Instructions...
Страница 86: ...Setting the teachpoints Checking and adjusting the gripper offset 78 AssayMAP Bravo Platform Installation Guide...
Страница 113: ......
Страница 114: ...Agilent Technologies Installation Guide G5571 90001 Revision B March 2018...