Items of generation information are as follows:

Display

Description

Power

Current Output Power

EToday

Total Generation Capacity today

ETotal

Total Generation Capacity

ECh1Day/ECh2Day

Total Generation Capacity today in PV1/ PV2

VPV1 /VPV2

DC Input Voltage in PV1/PV2 channel

IPV1 /IPV2

DC Input Current in PV1/PV2 channel

VAC

AC Output Voltage

IAC

AC Output Current

FAC

AC Output Frequency

7.1.4.3 Query Interface

Press Ent on main interface for related information in query interface. Five choosing items on the

queryinterface: Inverter Info, Wifi Info, Error Record, Date Time and Set. Press UP and DOWN to select the

queryitem,press Ent to get in and Esc back to main

interface.

Inverter Info

In Inverter Info interface, it shows the inverter model type, version of master CPU (M), slave CPU (S),

version of DISP and SN No. of the inverter.

Wifi Info

In Wifi Info, it shows SN No. of monitoringmoduleand Internet IP address. Press Esc back to main interface.

Attention: SN in the WIFI Info interface means the SN of monitoringmodule, therefore the SN in the

inverter Info interface is the SN of the inverter. Please do not get them mixed up.

Содержание HNS TL Series

Страница 1: ...USER S MANUAL On Grid PV Inverter Anyhome Series HNSxxxxTL 1 xxxx 1000 1500 2000 2500 3000 3600 HNSxxxxTL xxxx 3000 3600 4000 5000 6000 7000 8000 Version 03 610100011008 V0 01 ...

Страница 2: ...em solutions to satisfy the consistently increasing demands for global energy The newly designed PV Inverter features itself with full load high efficiency high reliability and user friendly interface The maximum conversion efficiency of our inverter is up to 98 A user friendly installation interface professional industrial design and design for reliability mechanism give the Inverter Family a com...

Страница 3: ...OUNTING 7 4 1 SAFETY 7 4 2SELECTING THE APPROPRIATE MOUNTING LOCATION 7 4 3MOUNTING THE INVERTER WITH WALL MOUNTING BRACKET 9 5 ELECTRICAL CONNECTION 10 5 1 OVERVIEW OF THE CONNECTION AREA 10 5 2 CONNECTION TO THE PUBLIC GRID AC 11 5 3 CONNECTION TO THE PV GENERATOR DC 错误 未定义书签 7 SYSTEM DIAGRAM 18 8 OPERATION 19 8 1 SERIESOPERATION 20 8 3 LCD BACKLIGHT CONTROL 25 9 TECHNICAL DATA 25 10 TROUBLE SHO...

Страница 4: ...1 2 Target Group This manual is for qualified personnel The tasks described in this manual must only be performed by qualified personnel 1 3 Additional Information For more information about Afore products please download from our website www aforenergy com 2 Safety Instructions 2 1 Safety Precautions 1 All work on the inverter must be carried out by qualified electricians And ensure that children...

Страница 5: ... modifications to the inverter not recommended by Afore or the installation ofcomponents not sold by Afore New Energy void the warranty claims 2 2 Explanations of Symbols Symbol Explanation Danger of Electric Shock The inverter is directly connected with the public grid All work on the inverter must be carried out by qualified personnel only Beware of hot surface The inverter can become hot during...

Страница 6: ...xx 1000 1500 2000 2500 3000 3600 4000 5000 and BNTxxxKTL xxx 005 006 008 010 assembly parts are as listed below Object Quantity Description Object Quantity Description A 1 Solar inverter B 1 Wall mounting bracket C 1 User manual D 1 Certificate of inspection E 1 Installation diagram F 1 Notice for installation G 1 Warranty card H 1 AC connector I 3 Plastic Expansion Tube J 3 Tapping screw K 1 Secu...

Страница 7: ...l only in compliance with national or local standards and regulations CAUTION Danger of burn injuries due to hot enclosure parts Install the inverter so that it cannot be touched inadvertently Risk of injury due to the heavy weight of the inverter Take the inverter s weight into account for mounting Weight of inverter refers to chapter 9 4 2Selecting the Appropriate Mounting Location Consider the ...

Страница 8: ...tall the inverter directly exposing to strong sunshine is not recommended the excess heating might lead to power reduction Leave enough effective space around the inverter for better ventilation Vertical installation wiring area must be downside lateral installation is not allowed in backward tilted installation tilt angle should not exceed 30 degrees Forward tilted horizontal or inverted installa...

Страница 9: ...n and drill the holes for the screws 2 Fix the wall mounting bracket with the equipped self tapping screw 3 Hang the inverter to the mounting bracket and ensure the slot is fitted on the bracket 4 Check to ensure the inverter is correctly seated Make sure to lock it with the security screws See the figure below ...

Страница 10: ...mm2 cooper wire and that of external ground conductor should be 4mm2 cooper wire 5 On both sides of inverter to the grid and PV array there must be between circuit breaker and surge protector and during inverter electrical connections circuit breakers on both sides should be disconnected to prevent electric shock 6 Before connecting the inverter to PV arrays and public grid make sure the polarity ...

Страница 11: ...or connecting the PV strings c Junction box for RS485 connection and AC connection d AC connection e DC Switch optional 5 2 Connection to the Public Grid AC 5 2 1 Conditions for Connection CAUTION Unit Disconnection From Load Disconnect the circuit breakers and switches of inverters AC and DC sides 5 2 2 Connection to Public Grid AC Measure the grid voltageto make sure within the permissible range...

Страница 12: ...ping length is 7mm 2 AC line goes through AC terminal waterproof head and cap 3 Connect AC line Live line L Neutral line N and Ground Wire PE according to polarity Tighten the screws to ensure a solid connection Guarantee not to fall off if pulling PE ...

Страница 13: ...e cap make sure they clip closely together 5 Connect AC connector to AC terminal of the inverter Ensure firm insertion 5 3 Connection to the PV Generator DC CAUTION Unit Disconnection From Load Disconnect circuit breakers and switches on both DC and AC sides ...

Страница 14: ...TL 1 500 14 HNS3000TL 1 500 17 HNS3600TL 1 550 17 Anyhome Series Double MPPT trackers HNS3000TL 550 12 x2 HNS3600TL 550 15 x2 HNS4000TL 550 16 x2 HNS5000TL 550 18 x2 HNS6000TL 550 18 x2 HNS7000TL 550 18 x2 HNS8000TL 550 18 x2 5 3 2 Assembling the DC Plug Connector In order to connect to the inverter all connection cables of the PV modules must be equipped with the DC plug connectors provided You w...

Страница 15: ...uctions Prepare the DC wire to connect the positive and negative DC arrays Stripping length is 12 15mm sectional area is 4 mm2 as below Insert the DC wire to metal connecting tube Make sure all line heads are in the connecting tube as picture blow Female Connector Male Connector Stripping length is 12 15mm sectional area is 4mm2 Positive PV Array Negative PV Array ...

Страница 16: ... 5 3 3 Connecting the PV Generator DC DANGER Danger to life due to high voltage in the inverter Before connecting the PV generator ensure that the AC DC circuit breaker is switched off Notes 1 Make sure that you have disconnected circuit breakers and switches on both DC and AC sides 2 Check the connection cables of the PV modules for correct polarity and that the maximum input voltage of the inver...

Страница 17: ...00 The device is equipped with 2 groups of DC DC A and DC B of connecting sockets for DC input and each group contains a pair of connecting sockets DC and DC Group A and B are respectively connected to two DC arrays as picture below Connect PV and PV in PV Array 1 to the positive and negative poles of DC A and those of PV2 to those of DC B ...

Страница 18: ... Inverter always tries to convert the maximum power from the PV array 3 DC Breaker The current per DC string does not exceed 25A 4 AC Breaker Refer to the following table to choose the AC breaker Refer to the following table to choose the AC breaker Type Max AC Current A Rate current of AC breaker A Anyhome Series Single MPPT tracker HNS1000TL 1 6 9 HNS1500TL 1 9 16 HNS2000TL 1 12 20 HNS2500TL 1 1...

Страница 19: ...KV DC side nominal discharge current 20KA second grade lightning protection protection voltage 3 2KV 6 The wiring distance between the inverter and the distribution box should be at least 5 meters 7 Utility Referred to as grid in this manual i e the media your electric power company provides power to your place Please note that Inverter can only be connected to low voltage systems namely 220 230Va...

Страница 20: ...r to 7 1 4 1 for specific operations The inverter starts up and feed into the utility grid automatically when all the necessary conditions of normal operation for the inverter is fulfilled 3 Check whether the display and LEDs are indicating a normal operating state Sign Color Instructions POWER Green On Normal Operation RUN Yellow On Normal Grid connection FAULT Red Flash Check wiring 7 1 3 Anyhom...

Страница 21: ... some faults Please wait 10 minutes to be sure whether the fault is temporary If yes inverter will automatically restart again If not contact after sales personnel RUN LED Flashes Yellow When situation is satisfied for inverter to connect grid RUN LED will turn on If the yellow RUN LED doesn t turn on it means the inverter doesn t connect to grid 7 1 4 Anyhome Series LCD Display Inverter will star...

Страница 22: ...me setting is completed press Ent to exit and system will enter into the main interface as below Starting second time LCD will enter main interface directly in five seconds after initialization Operation status and generation information of inverter will be shown on the main interface The operation status will be displayedin the first line of the main interface Display Description Waiting Countdow...

Страница 23: ...ation in query interface Five choosing items on the queryinterface Inverter Info Wifi Info Error Record Date Time and Set Press UP and DOWN to select the queryitem press Ent to get in and Esc back to main interface Inverter Info In Inverter Info interface it shows the inverter model type version of master CPU M slave CPU S version of DISP and SN No of the inverter Wifi Info In Wifi Info it shows S...

Страница 24: ...ease contact after sales if the problem still exists Date Time It shows current date and time Press Esc back to query interface Set Set interface is as follows Items in set interface are as follows Display Description Date Time Date and time setting Safety Country and standard setting Energy K Coefficient set of power generation correction Freq Range Frequency limit setting Volt Range Voltage limi...

Страница 25: ...ions HNS1000TL 1 HNS1500TL 1 HNS2000TL 1 HNS2500TL 1 HNS3000TL 1 HNS3600TL 1 Input DC Max DC Power W 1200 1800 2400 3000 3600 3600 Max DC Voltage V 500 500 550 500 500 550 Rated Recommended Voltage V 360 360 360 360 360 380 MPPT DC Voltage Range V 50 400 90 400 120 400 120 400 120 400 120 450 Start up DC Voltage V 60 60 150 150 150 150 Turn off DC Voltage V 45 45 120 120 120 120 Max DC Current A 1...

Страница 26: ...protection Aluminium RCD Internal Weight kg 9 12 Ambient Temperature Range 25 60 Humidity range 0 100 Topology Transformerless Communication Interface RS485 WI FI Wire Ethernet GPRS optional Cooling Concept Convection Noise Emission dB 28 Elevation Up to 2000m without derating Anyhome Series Double MPPT Trackers Electrical Specifications HNS3000TL HNS3600TL HNS4000TL HNS5000TL HNS6000TL HNS7000TL ...

Страница 27: ...W 30 30 30 30 30 30 30 Power consumption Power consumption at Night W 1 1 1 1 1 1 1 Power consumption at Standby W 6 6 6 6 6 6 6 Power Efficiency Max Efficiency 98 03 98 03 98 03 98 03 98 03 98 03 98 03 Euro Efficiency 97 60 97 60 97 60 97 60 97 60 97 60 97 60 MPPT Efficiency 99 9 99 9 99 9 99 9 99 9 99 9 99 9 Safety and protection Safety Standard EN IEC 62109 1 2 EMC Standard EN IEC 61000 6 EN IE...

Страница 28: ...th local dealer if error remains the same after several reset Bus Fault AC side incorrect wiring Machine failure 1 Disconnect the input output switch check the AC side wiring and reseat the plug to rule out bad contact 2 Please contact with local dealer if error remains the same after several reset Over Current 1 AC side incorrect wiring 2 Electricity grid abnormal 3 Machine failure 1 Disconnect t...

Страница 29: ...isconnect the input output switch check the AC side wiring and reseat the plug to rule out bad contact 2 After electricity grid returns to normal the machine will automatically restart 3 Please contact with local dealer if error remains the same after several reset Relay 1 2 Fault 1 Machine failure 1 Please contact with local dealer if error remains the same after several reset M Grid Freq Fault 1...

Страница 30: ...Inverter serial number Inverter SN Number Customer Information The contents of this manual are subject to change without further notice For Afore latest product information please visit our website www aforenergy com Afore New Energy Technology Co Ltd www aforenergy com ADD No 2755 Sanlu Rd Minhang District Shanghai China 201112 TEL 86 21 54326236 FAX 86 21 54326136 E MAIL info aforenergy com ...

Страница 31: ...damage warranty seal 2 5 Change or remove specification label serial number SN 2 6 Product malfunction or damage due to disobey to relevant laws and regulations or technical requirements in power plant design construction or installation works 2 7 Solar panels input parameters out of the inverter s allowed range 2 8 Product malfunction or damage due to installation on movable device or in vibratio...

Страница 32: ...ease visit www aforenergy com for dealer installer s contact details Of course customers may also contact Afore head quarter if they need help or advice 5 Force Majeure Force majeure is not artificially unavoidable and insurmountable objective conditions In addition it is the loss that even if the use of methods of prevention and attention cannot prevent It includes the following a earthquakes flo...