6.13 Adjustments before First Firing (Gas Operation)
Adjustments Before First Firing
1. Ensure that the gas supply company has carried out the supply line vent operations,
eliminating air or inert gases from the piping.
2. Slowly open the manual valves situated upstream of the gas train.
3. Adjust the minimum gas pressure switch shown in Figure 6-17 to the start of the scale.
Figure 6-17: Minimum Gas Pressure Switch
4. Adjust the maximum gas pressure switch shown in Figure 6-18 to the end of the scale.
Figure 6-18: Maximum Gas Pressure Switch
5. Adjust the air pressure switch shown in Figure 6-19 to the start of the scale.
Figure 6-19: Air Pressure Switch