Preparing the installation site |
27
Pre-stamped inlets in the housing edge
The housing features pre-stamped inlets in the middle of the upper and lower edge, which can be opened with uni-
versal pliers or a similar tool and are used for inserting the power and data cable.
Decide before carrying out the installation how the pow-
er and data cables should be fed into the wallbox.
Carefully remove the desired plastic tabs before
starting the installation.
You can combine the inlets as required: even if you
want to feed the power line through the inlet at the
top edge or directly through the rear, you can run the
data and control cables via the lower inlets.
Preparing the installation site
As a matter of principle, the electrical supply cable in the domestic power distribution must be switched off for the
entire duration of mechanical and electrical installation. The connection to the power grid must only be made live for
the purpose of commissioning, after electrical installation is complete.
DANGER!
Dangerous electrical currents
Always observe the 5 safety rules:
1
Cut power source
2
Secure all cut-off devices
3
Verify absence of voltage
4
Ground and short-circuit
5
Cover or bar access to adjacent components under voltage
Proceed as follows:
1
Prepare the drilling template for the cables, if
necessary.
J
If directly inserting the power line from behind,
cut the grommet marked
C
on the drilling
template.
J
If inserting the data and control cables, cut the
grommets marked
DATA
and
EXT. CONTROL
on
the drilling template.
C
A
B
DATA
170 mm
EXT. CONTROL
130 mm
230 / 400 V
130 mm