Installation and commissioning guide
1ZSC000562-AAK EN, REV. 2, 2019-07-03
73
10 Commissioning at site
10.1 Installation of the removed parts
Overview
Refer to the report from the preparations of the transformer before transportation to the site.
Procedure
1.
Remove all transport covers.
2.
Install all parts that where removed for transportation. Refer to the markings made to each part.
NOTE!
It is important that all parts are correctly installed, and in the same position as when they
were removed.
3.
Remove the drying agent from the motor-drive cabinet.
4.
If the transformer oil was removed for transportation, then fill the tap-changer and transformer with
transformer oil. Refer to
Preparations,
page
End of instruction
10.2 Connection of the electrical connections
Procedure
1.
Connect the motor-drive mechanism to the power supply.
2.
Connect the operational circuits to the motor-drive mechanism.
3.
Connect the external connections, refer to the site documentation.
End of instruction
Содержание VUBB
Страница 14: ...14 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Страница 28: ...28 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Страница 52: ...52 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Страница 60: ...60 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Страница 68: ...68 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Страница 72: ...72 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Страница 74: ...74 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Страница 76: ...76 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...