IEC15000029 V1 EN
2.
Exit back to the root menu.
3.
Select
Yes
in the save dialogue box.
Once the IED is in test mode the yellow Start LED starts to blink.
9.8.2.2
Enable forcing using TESTMODE function block
•
Use the TESTMODE function block, appropriately configured in PCM600/ACT.
It may be convenient to control the input on mentioned component from, for example,
an LHMI function key or similar during commissioning to quickly and easily enter
IED test mode.
9.8.3
How to change binary input/output signals using forcing
Once the IED is in IED test mode, the LHMI/PCM600 menus can be used to control
input/output signals freely.
9.8.3.1
Forcing by using LHMI
Editing a signal value directly
•
Edit the input/output value directly to select the desired logical level, by doing
following:
1.
Select the value line of the desired signal, see figure
.
2.
Press the Enter key to edit the value.
Section 9
1MRK 504 160-UEN -
Testing IED operation
60
Transformer protection RET650 2.1 IEC
Commissioning manual
Содержание RET650 2.1 IEC
Страница 1: ...Relion 650 series Transformer protection RET650 2 1 IEC Commissioning manual ...
Страница 2: ......
Страница 24: ...18 ...
Страница 32: ...26 ...
Страница 48: ...42 ...
Страница 52: ...46 ...
Страница 72: ...66 ...
Страница 110: ...104 ...
Страница 116: ...110 ...
Страница 125: ...119 ...